REPORT
CORPORATE SERVICES DEPARTMENT
Meeting:
GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date:
June 19, 2006
Report #: COD-041-06
File#_
By-law #,-9.. Of') b --, AI 6-
c;.,Pfi - ~ '-0 b
Subject:
CL2006-32, FOOTBALL FIELD, COMMUNITY PARK, BOWMANVILLE
Recommendations:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-041-06 be received;
2. THAT Dol Turf Restoration Ltd, Bond Head, Ontario with a total revised bid in the
amount of $612,061.12 (Plus G.S.T.), being the lowest responsible bidder
meeting all terms, conditions, and specifications of Tender CL2006-32, be
awarded the contract for the Football Field, Community Park, Bowmanville,
Ontario as required by the Engineering Department;
3. THAT funds required in the amount of $675,000.00 be drawn from Engineering
2006 Capital Account #110-32-325-83252-7401;
4. THAT additional funds required in the amount of $255,000.00 be provided from
the Development Charges for Park Development Reserve Fund in the amount of
$229,500.00 and $25,500.00 from the Engineering Parks Capital Reserve Fund;
and
5. THAT the attached By-law marked Schedule "A" authorizing the Mayor and the
Clerk to execute the necessary agreement be approved.
REPORT NO.: COO-041-06
Submitted by: ~r.ALJi)
Marie~~, H.B.Sc., C.M.O.
Director of Corporate Services
,-,.I' , Awln
061 N~~or, B.BA, f!;;,
41~
A.S. Cannella, C.E.T.
Director of Engineering Services
MM/NT/ASC/LB/km
PAGE 2
Reviewed by:
F nklin Wu,
f Chief Administrative Officer
REPORT NO.: COO-041.Q6
PAGE 3
BACKGROUND AND COMMENT
Tender specifications were provided by Totten Sims Hubicki Associates for the Football Field,
Community Park, Bowmanville, Ontario, as required by the Engineering Department and as
shown on the map below:
~
c
't
=
~
Jt
~~~
s
BOWMANVILLEi,
Bowmanville Community Park (2006)
Tenders were advertised in local papers, as well as electronically. Subsequently, tenders were
received and tabulated as per letter from Totten Sims Hubicki Associates Schedule "B"
attached.
The total project cost, including Project Administration, and costing allocation is $930,000.00.
The funding will be provided as follows and is as outlined in the memo from Engineering
Services and the letter from Totten Sims Hubicki Associates marked Schedule "B".
2006 Budget Account # 110-32-325-83252-7401
Engineering Parks Capital Reserve Fund
Development Charges for Park Development
Reserve Fund
$675,000.00
$ 25,500.00
$229.500.00
$930,000.00
REPORT NO.: COO-041.Q6
PAGE 4
As the total tender exceeds the budget allocation it is recommended that the provisional items
(retaining wall and railing, area drain and pipe) in the amount of $112,774.15 be deleted from
the contract which reduces the tender price to $612,061.12.
The budget over-run is attributed to not having preliminary design available at the time the
budget estimate was prepared as well as the current upward trend of construction costs due to
the amount of work contractors already have secured for the year.
The low bidder has previously performed satisfactory work for the Municipality of Clarington.
The Director of Finance has reviewed the funding requirements and concurs with the
recommendation. Queries with respect to department needs, specifications, etc., should be
referred to the Director of Engineering.
After further review and analysis of the bids by the Engineering Department, Totten Sims
Hubicki Associates and Purchasing, it was mutually agreed that the low bidder, Dol Turf
Restoration Ltd, Bond Head, Ontario, be recommended for the contract for the Football Field,
Community Park, Bowmanville, Ontario.
Schedule "A" By-law
Schedule "B" Memo
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T(905)623-3379 F (905)623-4169
Schedule "A"
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-LAW 2006-
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Dol Turf
Restoration Ltd, Bond Head, Ontario, to enter into agreement
for the Football Field, Community Park, Bowmanville Ontario.
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON HEREBY ENACTS AS
FOLLOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Dol Turf Restoration Ltd, Bond Head, Ontario, and said
Corporation; and
2. THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this 26th day of June, 2006.
By-law read a third time and finally passed this 26th day of June, 2006.
John Mutton, Mayor
Patti L. Barrie, Municipal Clerk
SCHEDULE "B"
Q~il/glOn
MEMO
TO:
Louann Birkett, Purchasing Manager
FROM:
Peter Windolf, O.A.L.A., Manager of Park Development
DATE:
June 13, 2006
SUBJECT: FOOTBALL FIELD, BOWMANVILLE COMMUNITY PARK
CL2006-32
The Engineering Services Department has reviewed the recommendation
provided by TSH and offers the following comments.
We concur with the recommendation to award the contract to Dol Turf
Restoration Ltd. in the amount of $612,061.12 exclusive of G.S.T. for the Football
Field project for 2006.
A contingency amount of approximately 5.0% is carried forward for the project.
The budget allocated for Phase 2 of the park development also included the
provision of baseball field scoreboards including the construction of support
structures as well as the construction of an access road for the installation and
maintenance of the hydro transformer for the park. . Therefore, including design,
tender fees, contract administration fees and previously committed costs, the
engineering department advises the following Municipal breakdown for the above
referenced project;
Phase 2 - Bowmanville
Community Park
Account 11032325832527401
Total Project $930,000.00
Amount
BudQet Amount $675,000.00
Estimated $255,000
Budget Shortfall
Football Field, Bowmanville Community Park
CL 2006-32 2
SCHEDULE "B"
June 13, 2006
The estimated budget shortfall of $255,000 will be taken from the Development
Charges for Park Development Reserve Fund ($229,500) and the Engineering
Parks Capital Reserve ($25,500.
We recommend the report to Council move forward based on the above costs
and funding arrangements. Attached for your files is the recommendation
provided by TSH. Should you have any further question, please feel free to
contact the undersigned.
Regards,
~\J0~
Peter Windolf, O.A.L.A.
Manager of Park Development
BB/sc
Attachment
cc Ron Albright, P. Eng., Totten Sims Hubicki
Nancy Taylor, Director of Finance
CORPORATION OF THE MUNICIPALITY OF cLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L 1C 3A6 T(905)623-3379
II
lilt
SCHEDULE "B"
Totten Sims Hubicki Associates
513 DIVision Street,
Cobourg, Ontario, Canada K9A 5G6
(9Q5) 3:22121 Fax: (905) 372-3621
Email: cobourg@tsh.ca www.tsh.ca
engineers
architects
planners
June 13,2006
Mr. A. S. Cannella, C.E.T.
Director of Engineering Services
Corporation of the Municipality of Clarington
40 Temperance Street
BOWMANVILLE, Ontario, L I C 3A6
Dear Mr. Cannella:
Re: Football Field, Bon-manville
COli tract CL2006-32
Municipality of Clarington
Tenders for the above project were opened at the Municipal Offices on Friday June 9, 2006 at 2: IS p.m. A
list of the bids received is provided in the table below. All numbers are exclusive ofGST.
BIDDER TOTAL BID AMOUNT
Dol Turf Restoration Ltd. $724,835.27
Bond Head, ON
Rutherford Contracting Ltd. $810,902.51
Gonnlev, ON
S & F Excavating Ltd. $829,024.00
KinR City, ON
A-Con Construction Limited $1,119,889.40 *
W oodbridRe, ON
* Extension Error
The accepted bids received from Purchasing have been reviewed and are in order. Dol Turf Restoration
Ltd. completed the South Courtice Soccer Facility project, Contract CL2003-15, for the Municipality of
Clarington in 2004. Their perfonnance on the contract was satisfactory, Dol Turf Restoration Ltd. have
also completed similar type work for the City of Vaughan, Town of Collingwood and City of Hamilton
and those references contacted also confirmed the contractor's performance on other projects to be
satisfactory.
Mr. A.S. Cannella, C.E.T.
June 13,2006
SCHEDULE" B"
2
Project costs based on Dol's bid and previously committed funds for Phase 2 of the park are summarized
as follows:
Description
Construction Costs per Contract CL2006-32
Provisional Items to be removed from Contract
(Retaining Wall and Railing, Area Drain and Pipe)
Sub-Total (revised Tender Amount)
Detailed Design, Tendering & Approvals TSH
Project Number 42-80446 to May 27, 2006
Contract Administration (Estimated)
Contingencies (Estimated)
Sub-Total (Football Field Construction Costs)
Previously Committed Funds - Scoreboard
Constnlction, Scoreboard Supply, Access Road,
Design and Administration
Total Estimated Project Costs
Clarington Budget Amount
Estimated Budget Overrun
Cost
$724,835.27
$112,774.15
$612,061.12
$20,800.66
$52,000.00
$31,377.22
$716,239.00
$213,761.00
$930,000.00
$675,000.00
$255,000.00
The project costs are estimated to be $255,000.00 over the available budget. The budget overrun can be
attributed to not having a preliminary design available at the time the budget estimate was prepared as well
as the current upward trend of construction costs due to the amount of work contractor's already have
secured for the year.
The commencement of Phase 2 construction of the Bowmanville Park is a vital pal1 of the growing
recreational movement present in the Municipality of Cia ring ton. It is suggested that any necessary
adjustments or re-allocation of funds is provided to ensure the completion of Clarington' s only community
football field.
It is recommended that the revised tender in the amount of$612,061.12 (exclusive ofG.S.T.) be awarded
to Dol Turf Restoration Ltd. of Bond Head, Ontario.
Deposit cheques or bid bonds should be retained for the low and second low bids until the Contract has
been executed.
Should you require any further information, please contact the undersigned.
Yours truly,
/~
Ron Albright, P.En
Project Engineer
RA/cg