HomeMy WebLinkAbout2006-109
THE CORPORATION OF THE MUNICIPALITY OF CLARINGTON
BY-lAW 2006-109
Being a By-law to authorize a contract between the
Corporation of the Municipality of Clarington and Wayne
Electric Co. Limited, Carlisle, Ontario, to enter into agreement
for the Harvey Jackson Ball Diamond Lighting.
THE CORPORATION OF THE MUNICIPALITY OF ClARINGTON HEREBY ENACTS AS
FOllOWS:
1. THAT the Mayor and Clerk are hereby authorized to execute, on behalf of the
Corporation of the Municipality of Clarington and seal with the Corporation Seal, a
contract between, Wayne Electric Co. Limited, Carlisle, Ontario, and said
Corporation; and
2. THAT the contract attached hereto as Schedule "A" form part of this By-law.
By-law read a first and second time this 15th day of May, 2006.
By-law read a third time and finally passed this 15th day of May, 2006.
/1l{(;~
~on, Mayor
&~.
C.' Anne Greenf e, Deputy Clerk
Standard construction document eeDe
Clfll-!lJgton
Municipality of Clarington
EXECUTED CONTRACT
Stipulated price contract
Project: TENDER CL2006 -12
HARVEY JACKSON BALL DIAMOND LIGHTING
rD'"
,.
~:!: ': ;:'
,
.. . ~;
<wyaCCDC2c:opyrishtsmlhere. TheapJ6caliooof
lbesea1dem.:mraleslbeimfdirJnofthe~.proposiIg
lbeuseilllhis doaJmmthal it OOillllllnnll'! and
~fonnofCCOC2-1994~ktlbeeldeDt
_..,.akeraIKm, alUiIimsoclllOdilil:Won; lire set fOrth
m~~
[s[sD[s
Canadian construction documents committee
Reprint 1998
[s[sD[s
Canadian construction documents committee
The Canadian Construction Documents Committee is a joint committee composed of owners and representatives
appointed by:
The Association of Consulting Engineers of Canada
The Canadian Construction Association
Construction Specifications Canada
The Royal Architectural Institute of Canada
Committee policy and procedures are directed and approved by the constituent organizations.
This document has been endorsed by each of the above organizations.
Enquiries should be directed to:
The Secretary
Canadian Construction Documents Committee
75 Albert Street
Suite 400
Ottawa, Ontario
KIP 5E7
Tel: (613) 236-9455
Fax: (613) 236-9526
www.ccdc.org
Standard Construction Document CeDe 2 . 1994
TABLE OF CONTENTS
PART 4
GC4.1
GC4.2
AGH.ElMEI\T BETWEEN O\V'ER AND CONTRA.CrOR
A-1 The Work
A-2 Agreements and Amendments
A-3 Contract Documents
A-4 Contract Price
A-5 Payment
A-6 Receipt of and Addresses for Notices
A-7 Language of the Contract
A-8 Succession
m:FI;\ilTlO:\S
1. Contract
2 Contract Documents
3 O~Yner
4 Contractor
5. Subcontractor
6. Supplier
7. Consultant
8 Project
9. Work
10 Place of The \Vork
II. Product
12. Provide
13. Contract Price
14. Contract Time
IS. Working Day
16 Supplemental1nstruction
17. Change Order
18. Change Directive
19. Substantial Performance of the Work
20. Value Added Taxes
PART::;
GC5.1
GC5.2
GC5.3
GC54
GC5,5
GC 5,6
GC5,7
GC5.8
GC 5.9
PART!.
OC6.1
OC6.2
OC6.3
OC6.4
GC6.5
PART 7
OC7,]
GC7.2
!}ART8
GC 8,1
OC8.2
OC8.3
GE"'ER.\LCONonIO:--'S 01' [TIE STlPLLATEH
[}RICE CONTRACI
P.-\.RTl
GC 1.1
GC 1.2
GCU
OCI,4
P,\RT 2
GC2,1
GC2,2
GC2.3
OC2.4
PART 3
OC3,1
OC3.2
GC3.3
OC3,4
GC3,5
GC 3.6
GC3.7
GC3.8
OC3.9
OC3.IO
GC3.11
OC3.12
GC3.13
GC3.14
GE:'\TRAL I'ROVIS!ONS
Contract Documents
Law of The Contract
Rights and Remedies
Assignment
PART 9
OC9.1
OC9.2
OC9.3
PART 10
GC ]0.1
GC 10.2
GC 10.3
GC 10.4
ADMINlSTRATIOI\ OF rUE, CONTRACT
Authority of The Consultant
Role of The Consultant
Review and Inspection of The Work
Defective Work
PARTll
GC 11,1
GC 112
EXECLTlO'i OF THE '\-,"ORK
Contra] of the Work
Construction by Owner or Other Contractors
Temporary Supports, Structures. and Facilities
Document Review
Construction Schedule
Construction Safety
Supervisor
Subcontractors and Suppliers
Labour and Products
Documents at The Site
Shop Drawings
Use of the \Vork
Cutting and Remedial Work
Cleanup
1~;\RT 12
OC 12.1
GC ]2.2
GC 12,3
ALLo-W..1o..NCES
Cash Allowances
Contingency Allowance
P.-\ ){?;'lENT
Financing Information Required of the Owner
Applications for Progress Payment
Progress Payment
Substantial Perfonnance of the Work
Payment of Holdback upon Substantial Perfonnance of the Work
Progressive Release of Ho]dback
Final Payment
Withholding of Payment
Non-confonning Work
C1.IANGTS IN Tll E \VORK
Changes
Change Order
Change Directive
Concealed or Unknown Conditions
De]ays
[)EFALLT :\OTICI<:
Owner's Right to Perform The Work Stop The Work, or
Terminate The Contract
Contractor's Right to Stop the Work or Terminate The
Contract
DISPlJTE RESOLUI!Ol\
Authority of Tile Consultant
Negotiation, Mediation, and Arbitration
Retention of Rights
PROTECTJ01\ OF PERSONS i\NJ) PRO PERT)
Protection of\Vork and Property
Damages and Mutual Responsibility
Toxic and Hazardous Substances and Materials
GOVEU'\'["G REGLLAT]O'\'S
Taxes and Dilties
Laws, Notices, Permits, and Fees
Patent Fees
Workers' Compensation
INSt'R.\::\'CE
Insurance
Bonds
UO'\DS
INBK\1!\lfF!C\T10N - WAIVER
Indemnification
Waiver of Claims
\l,I'arranl)'
\\/ARR,\NT\:
ceDC Copyright 1994
Must not be copied in whole or in part without the written pennission
01" the CCDC
Standard Construction Document eeDe 2 - 1994
AGREEMENT BETWEEN OWNER AND CONTRACTOR
For use when a stipulated price is the basis of pa)'ment
This Agreement made on the
5~
day of J0 n.e.
in the year
2006
by and between
Corporation of the Municipality of Clarington
hereinafter called the "(hncr"
and
Wayne Electric Co. Limited
hereinafter called the "Contractor"
The Oi-vner and the COI1(mcful' agree as follows:
ARTICLE A-I THE WORK
The Contractor shall:
1.1 perform the ~-Vork required by the Collirac; Doc1!mcl!f.s for
Tender CL2006-12
Harvey Jackson Ball Diamond Lighting
located at
6690 Regional Rd. 18 (Newtonville RD.)
Kendal, Clark Township
which have been signed by the parties, and for which
MJS Consultants Inc.
is acting as and is hereinafter called the "Conwlwn(' and
1.3
1.2 do and fulfill everything indicated by this Agreement, and
commence the W'lrk by the 3rd
day of
August
in the year 2006 and, subject to
adjustment in Contract Time as provided for in the Contract Documellls, attain S'ubstantial p(!fjormance
of {he g'ork, by the
30th
day of
August
intheyear 2006
eeDe 2 - 1994 File 00502
Ihis conlrue! i.\' prolee!ed by C'vpyrigfll Us~ oIa CCU(' 2 do{'umenIIJOI cun/ammg 0 CCD(' 2 copyrighl xeal con.\"lillltes an infringemem of('vpyrighl. Oniy siXn
this conlract if/he document cover page bear.\' a ('('DC 2 copyrigh/sev/to dt'mon.\lrale thm it IX intended hy Ihe parties {O be an uccurale and unamended persion oj
CCIJ(' 2 - }99.. excep/to Ihl:! ex/en/that any altera/Jom, mldiliu!I:J' or modijica/Jon.' ore .,e/ fur/h 1/1 ,wpplemt'n1al}' mnditio/lY
ARTICLE A-2
2.1 The Contract supersedes all prior negotiations, representations, or agreements, either written or oral, relating
in any manner to the FVork, including the bidding documents that are not expressly listed in Article A-3 of the
Agreement - CONTRACT DOCUMENTS.
2.2 The Contract may be amended only as provided in the COl1tract DOCWJ7(;'ll{Y.
ARTICLE A-3
3.1 The following are the ComraaDOCUlnents referred to in Article A-I of the Agreement - THE WORK:
. Agreement Between Owner and ComraclOr
. Definitions
. The General Conditions of the Stipulated Price Contract
A. Tender Form (Reference CL2006-12)
General, Pages 1 and 2 (Reference CL2006-12)
Itemized Bid, Pages 3 through 6 (Reference CL2006-12)
Agreement to Bond, Page 7 (Reference CL2006-12)
Schedule of Tender Data, Page 8 (Reference CL2006-12)
B. Standard Terms and Conditions (Reference CL2006-12)
C. Instructions To Bidders (Reference CL2006-12)
D. Special provisions - General (Reference CL2006-12)
E. Electrical General Requirements, Section 16000 (Reference
CL2006-12)
F. Basic Materials & Methods, Section 16005 (Reference CL2006-12)
G. Lighting Systems and Schedules, Section 16010 (Reference
CL2006-12)
H. Plans
Drawing No. E-1
,
(Insert here, attaching additional pages If required, a list ident~fying all other Contract Documents e.g.
Supplementary Conditions; Specifications, giving a list of contents with section numbers and titles,
number of pages, and date; Drawings, giving drawing number, title, date, revision date or mark;
Addenda, giving title, number, date)
CCDC 2 - 1994 File 00502
2
Thi.\' crlntract iI protected by CoPyrilihl Ule oIa CeDC' 2 documeni not comaining a CCDC 2 copyright .Ieal con.niWte,I' an infringement ofCopyrWht, Only.\ign
thiS comracl it the documem cover palie bears a cca' 2 copyright seal to dem<Jm'lrate Ihot il is l/JIended hy Ihe parties to be an acmrme and unamended 1'asion of
ceLX:' 2 - 19"N excepl 10 Ihe extent thai any alteration\', additiom or modijicolilm.,' are ,\'eJ jiJnh in supplemel7lary conditiom
ARTICLE A-4
4.1 The Con/raet Price, which excludes Value Added Tayes, is:
One hundred and forty eight thousand, six hundred
dollars
and
zero cents.
s
148,600.00
4.2
JIa/uc Added Taxes (of
7
%) payable by the (hrner to the Commc!or are:
Ten thousand, four hundred and two
dollars
and
zero cents.
s
10,402.00
4.3 Total amount payable by the Ohner to the Contrac!or for the construction of the JVork is:
One hundred and fifty nine thousand and two
dollars
and
zero cents.
$
159,002.00
4.4 All amounts are in Canadian funds.
4.5 These amounts shall be subject to adjustments as provided in the COIl/ract f]ocurnents.
ceDe 2 - 1994 File 00502
3
This con/racr is prOlected by Copyright. Use ala ceDe 2 do,'umenl nul wnlaining a CeDe 2 copyrighl seal mn.\lilules an infringement ofCopyrifi/ll. On,)} sign
ihis cOn/racl if the documenl cOl'er page beaY.\' a CeDC 2 copynghi seal 10 demons/rale that II i.1 in/ended by the ponies 10 be an accurate and unamended ven-ion oj
CCDC 2 19').j excep/lo Ihe ex/en/lhal anyallaaiions. addi/Jan.\ or modifications are seilorlh in .wpplementary condilions
ARTICLE A-5 PAYMENT
5.1 Subject to the provisions of the Contract Documents, and in accordance with legislation and statutory
regulations respecting holdback percentages and, where such legislation or regulations do not exist or apply,
subject to a holdback of ten (10 %) the Owner shall in Canadian funds:
.1 make progress payments to the Cont/'Qc'tol" on account of the Contract Price when due in the amount
certified by the Consultant together with such Vallie Added Taxes as may be applicable to such payment,
and
.2 upon Substantial Performance of {he tVork, pay to the Contractor the unpaid balance of the holdback
amount when due together with such Value Added Taxes as may be applicable to such payment, and
.3 upon the issuance of the final certificate for payment, pay to the CollfraclOr the unpaid balance of the
('omract price when due together with such Vallie .Added Taxes as may be applicable to such payment.
5.2 In the event of loss or damage occurring where payment becomes due under the property and boiler insurance
policies, payments shall be made to the CO!!traclOr in accordance with the provisions of G(;I I.! -
INSURANCF
5.3 Interest
.1 Should either party fail to make payments as they become due under the terms of the Controcl or in an
award by arbitration or court, interest at zero percent ( 0 %) per
annum above the bank rate on such unpaid amounts shall also become due and payable until payment.
Such interest shall be compounded on a monthly basis. The bank rate shall be the rate established by the
Bank of Canada as the minimum rate at which the Bank of Canada makes short term advances to the
chartered banks.
.2 Interest shall apply at the rate and in the manner prescribed by paragraph 5.3.1 of this Article on the
amount of any claim settled pursuant to Pnn ~ tll' tbe (;cn~'r:jl ('ondltlons LHSPLTL f(CSOLUT10\
from the date the amount would have been due and payable under the Contract. had it not been in dispute,
until the date it is paid.
eeDe 2 - 1994 File 00502
This contract i.\' pmt~d~d by Copyright. [}I'e uIa CCDC 2 documenl nm containing a CCDC 2 wpynghl seal con,l'IIlul~s an inJhngemem oj Copyright. Oniy sl[;:n
/his wl/lracllj"the document cova page bears a CCDC 2 mpyriKh/ .I'ear /0 demons/rale thai i/ is inlended h;.- the parties to he an accurate and unamemkd venion o(
CCOC 2 - J994 excepttu the extent thai ary' al/eratwn.\, addilions or modificatl(ms are .WI jiirth in supplementary wndilium.
4
ARTICLE A-6 RECEIPT OF AND ADDRESSES FOR NOTICES
6.1 Notices in writing between the parties or between them and the COn'lUltant shall be considered to have been
received by the addressee on the date of delivery if delivered to the individual, or to a member of the firm, or
to an officer afthe corporation for \vhom they are intended by hand or by registered post; or if sent by regular
post, to have been delivered within 5 rVorking Days of the date of mailing when addressed as follows:
The Owner at
40 Temperance Street
Bowmanville, Ontario
L1C 3A6
The Comractor at
1559 Milburough Line
P.O. Box 220
Carlisle, Ontario
LOR lHO
The CO/lSultanf at
7305 Woodbine Avenue
Suite 200
Markham, Ontario
L3R 3V7
ARTICLE A-7 LANGUAGE OF THE CONTRACT
7.1 When the Conrmet Documents are prepared in both the English and French languages, it is agreed that in the
event of any apparent discrepancy between the English and French versions, the English language
shall prevail.
. Complete this statement by striking out inapplicable term.
7.2 This Agreement is drawn in English at the request of the parties hereto. La presente convention est redigee en
anglais a la demande des parties.
ARTICLE A-8 SUCCESSION
8.1 The Contme! Documents are to be read into and form part of this Agreement and the whole shall constitute
the Contract between the parties, and subject to the law and the provisions of the Contract Documents shall
enure to the benefit of and be binding upon the parties hereto, their respective heirs, legal representatives,
successors, and assigns.
CCDC 2 - 1994 File 00502
5
This con/mc! i.I' prolec/ed by Copyright. U!ie ota CClX: 2 documem nal conJoming 0 CC[X~ 2 copyrighl.l'eol canslilllles an infringemen/ ofCopyrighl. Ollly .\'JglllhJ~'
,'on/rod if/he documm/ cover page bears a CeDe 2 ,'opyrigh/ sea! /0 demonstrate dlat i/ is in/ended by the parties /0 be an accurate and unamended wr.\ion ofCCDe 2
1994 e:<<:ep/ to the extent Ihal anyal/erations, miditiom Or modificationi>' are 8'el/orlh in slIpplememm:v conditions
In witness whereof the parties hereto and by the hands of their duly authorized representatives.
SIGNED AND DELIVERED
in the presence of:
OWNER
Corporation of the Municipality of
Clarin~
"gnat"" ~~
JQlfri Muttort;-~yor
~-:C-.'_
name lIna "tIe of per -nsign~
a
WITNESS
signature
Patti L Barrie. Clerk
name and title afperson signing
name and title of person signing
CONTRACTOR
Wayne Electric Co. Limited
,,~~
9t~
Wayne Neeb
President
WITNESS
name and title of person signing
/LktM
signature
signature
Alan Neeb - Manager
name and title of person signing
name and title oj'person ~'igning
N. B. Where legal jurisdiction, local practice, or (ftvner or Contractor requirement calls for:
(a) proof of authority to execute this document, attach such proof of authority in the form of a certified
copy of a resolution naming the representative(s) authorized to sign the Agreement for and on behalf
of the corporation or partnership; or
(b) the affIXing of a colporate seal, this Agreement should be properly sealed.
eeDe 2 - 1994 File 00502
6
This con/tad i~' protected by Copyrig!ll. U\'e o/a CCDC 2 docl/men/ nOI mnloining a CCDC 2 copyrighl .I'eal con,"lilules an infringemenl of'Copyright. OnfY.l'ign
this cOn/racl iflhe document cover page hearxa ceDe 2 c/Jpyrighl.\'eallO demons/rate that it is in/ended hy the par/iI:.\ 10 be an an'umle and unamended version oj
CeDC 2 - 1994 except to the e;r.tent that an}! al/eration.l, additions or modith-alions are .l'e/ jiJrrh in .\Uppfementw:v crmdi/iom-.
Standard Construction Document CeDe 2 - 1994
DEFI;';ITIONS
The following Definitions shall apply to all Contract Documents.
1. Contract
The Contract is the undertaking by the parties to perform their respective duties, responsibilities, and
obligations as prescribed in the Contract Documents and represents the entire agreement between the parties.
2. Contract Documents
The Contract Documents consist of those documents listed in Article A-3 of the Agreement - CONTRACT
DOCUMENTS and amendments agreed upon between the parties.
3. O,yoer
The (h-vner is the person or entity identified as such in the Agreement. The tenn Owner means the Owner or
the OJ.t'ner's authorized agent or representative as designated to the Contractor in writing, but does not include
the Consultant.
4. Contractor
The Contractor is the person or entity identified as such in the Agreement. The term Contractor means the
Contractor or the Contractor's authorized representative as designated to the Owner in \vnting.
5. Subcontractor
A Subcontractor is a person or entity having a direct contract with the Contractor to perform a part or parts of
the Tfork, or to supply Products worked to a special design for the Work.
6. Supplier
A Supplier is a person or entity having a direct contract \'yith the Contractor to supply Products not worked to a
special design for the Work.
7. Consultant
The Consultant is the person or entity identified as such in the Agreement. The Consultant is the Architect, the
Engineer, or entity licensed to practice in the province or territory of the Place of the Work. The term
Consultant means the Consultant or the Consultant's authorized representative.
8. Project
The Project means the total construction contemplated of which the Work may be the whole or a part.
9. Work
The Work means the total construction and related services required by the Contract Documents.
10. Place of the Work
The Place of the Work is the designated site or location of the Work identified in Article A-l of the Agreement
- THE WORK.
II. Prodnct
Product or Products means material, machinery, equipment, and fixtures forming the Work, but does not
include machinery and equipment used to prepare, fabricate, convey, or erect the Work, which are referred to as
construction machinery and equipment.
12. Provide
Provide means to supply and install.
eeDe 2 - 1994 File 00602
7
This contract is protecled by Copyright. Ule (~ra CCfX~ 2 document not conimning a CCDC 2 mpyright yeal cons/illites an infringemenl ofCopynght. Only ,\'Ign /his
contract i/"/he document COlier page bears a CCIX 2 copyright s('of /0 deff'lorlslrOle Ihal if i.1 inlended hy Jhe parties to be an accurate and unammd('d version ofCCDC 2
1994 e.xcept to the exten! thai anyalle.rmions, additiollS or modifications are sel!orth in supplementary conditions.
13. Contract Price
The Contract Price is the amount stipulated in Article A-4 of the Agreement - CONTRACT PRICE.
14. Contract Time
The Contract Time is the time stipulated in paragraph 1.3 of Article A-I of the Agreement - THE WORK from
connnencement of the Work to Substantial Perfonnance of the Work.
15. Working Day
Working Day means a day other than a Saturday, SWlday, or a holiday which is observed by the construction
industry in the area of the Place {if the Work.
16. Supplemental Instruction
A Supplemental Instruction is an instruction, not involving adjustment in the Contract Price or Contract Time,
in the fonn of specifications, dra\\rings, schedules, samples, models or written instructions, consistent with the
intent of the Contract Documents. It is to be issued by the Consultant to supplement the Contract Documents
as required for the performance of the Work.
17. Change Order
A Change Order is a written amendment to the Contract prepared by the Consultant and signed by the OMiner
and the Contractor stating their agreement upon:
a change in the Work;
the method of adjustment or the amount of the adjustment in the Contract Price, if any; and
the extent ofthe adjustment in the Contract Time, if any.
18. Change Directive
A Change Directive is a written instruction prepared by the Consultant and signed by the Owner directing a
change in the Work within the general scope of the Contract Documents.
19. Substantial Performance ofihe Work
Substantial Performance of the Work is as defined in the lien legislation applicable to the Place of the Work. If
such legislation is not in force or does not contain such definition, Substantial Performance of the Work shall
have been reached when the Work is ready for use or is being used for the purpose intended and is so certified
by the Consultant.
20. Value Added Taxes
Value Added Taxes means such sum as shall be levied upon thc Contract Price by the Federal or any
Provincial Government and is computed as a percentage of the Contract Price and includes the Goods and
Services Tax, the Quebec Sales Tax and any similar tax, the payment or collection of which is by the
legislation imposing such tax an obligation of the Contractor.
ceDe 2 - 1994 File 00602
8
Thix COn/raCI 6' protecled by Copyrigfu. Use ofa CeDC 2 documem nOI mfllaining a CClX' 2 ,"opyright.l'eof COfl,\'lilule.\' an in/ringen-lIml o(Copyright" Only sign this
conlraCI iflhe dOCl/menl cover pog!! b;;on- a CeDC 2 copyrighl seal 10 demonslra/e Ihol il i,l" inlended hy Ihe par/iI'S to be on Ga'l/rale and unamended \'ersl(m o(CCDC 2-
1994 excepllo Ihe extenl that any arteralions, addilio/l.l" or modijicmltHI.\"' an; Je/for/h in Jupplemenlury condi/Ions
Standard Construction Document CCDe 2 - 1994
GENERAL CONDITIONS OF THE STIPULATED PRICE CO:\TTRACT
PART I GENERAL PROVISIONS
GC I.I CONTRACT DOCUMENTS
1.1.1 The intent of the Contract Documents is to include the labour, Products, and services necessary for the
performance of the Work by the Contractor in accordance with these documents. It is not intended, however,
that the Contractor shall supply products or perform work not consistent with, not covered by, or not properly
inferable from the Contract Documents.
1.1.2 Nothing contained in the Contract Documents shall create any contractual relationship between:
.1 the Owner and a Subcontractor, a Supplier, or their agent, employee, or other person performing any of
the Work.
.2 the Consultant and the Contractor, a Subcontractor, a Supplier, or their agent, employee, or other person
performing any of the Work.
1.1.3 The Contract Documents are complementary, and what is required by anyone shall be as binding as if required
hyall.
1.1.4 Words and abbreviations which have well kno\VTl teclmical or trade meanings are used in the Contract
Documents in accordance with such recognized meanings.
1.1.5 References in the Contract Documents to the singular shall be considered to include the plural as the context
requires.
1.1.6 The specifications are that portion of the Contract Documents, wherever located and whenever issued,
consisting of the \vritten requirements and standards for Products, systems, workmanship, and the services
necessary for the perfonnance of the Work.
1.1.7 The drawings are the graphic and pictorial portions of the Contract Documents, wherever located and
whenever issued, showing the design, location, and dimensions of the Work, generally including plans,
elevations, sections, details, schedules, and diagrams.
1.1.8 Neither the organization of the specifications into divisions, sections, and parts nor the arrangement of
drawings shall control the Contractor in dividing the work among Subcontractors and Suppliers or III
establishing the extent of the work to be perfonned by a trade.
1. 1.9 If there is a conflict within Contract Documents:
. I the order of priority of documents, from highest to lowest, shall be
. the Agreement between the Ovvner and the Contractor,
. the Definitions,
. Supplementary Conditions,
. the General Conditions,
. Division 1 of the specifications,
. Divisions 2 through 16 ofthe specifications,
material and finishing schedules,
drawings.
eeDe 2 - 1994 File 00712
9
This conlraCl i.1 proleCled by Cop}righl. UI'e oIa CClX' 2 document not (YJf1laining a CC[)(~ 2 copyright seal conslitule.I' an infringemenr of Copyright. OnlY,I'if(l1lhi,\.
conJract if/he dncumenl cul'er page bears 0 CCOC 2 cupyr(r;hf seal Iv demon.\'lrale Iha/ i/ is inlended by the par/ie,I' JO be an accurale and unamended version (~ICCDC 2
1994 except 10 the extent thai airy ai/era/ions. additions or nwdiflcaliom are seljorth in supplemenlary wnditions.
.2 drawings of larger scale shall govern over those of smaller scale of the same date.
.3 dimensions shown on drawings shall govern over dimensions scaled from drawings.
.4 later dated documents shall govern over earlier documents of the same type.
1.] .10 The (hvner shall provide the Contractor, without charge, sufficient copies of the Contract Documents to
perroffil the Work.
1.1.11 Specifications, drawings, models, and copies thereof furnished by the Consultant are and shall remain the
Consultant's property, with the exception of the signed Contract sets, which shall belong to each party to the
Contract. All specifications, drawings, and models furnished by the Consultant are to be used only with
respect to the Work and are not to be used on other work. These specifications, drawings, and models are not
to be copied or altered in any manner without the written authorization of the Consultant.
1.1.12 Models furnished by the Contractor at the Owner's expense are the property of the Owner.
GC 1.2 LAW OF THE CONTRACT
1.2.] The law of the Place of the fVcn* shall govern the interpretation of the Contract.
GC 1.3 RIGHTS AND REMEDIES
1.3.1 Except as expressly provided in the Contract Documents, the duties and obligations imposed by the Contract
Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any
duties, obligations, rights, and remedies otherwise imposed or available by law.
1.3.2 No action or failure to act by the Owner, Consultant, or Contractor shall constitute a waiver of any right or
duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval
of or acquiescence in any breach thereunder, except as may be specifically agreed in writing.
GC 1.4 ASSIGNMENT
1.4.1 Neither party to the Contract shall assign the Contract or a portion thereof without the written consent of the
other, which consent shall not be unreasonably withheld.
PART 2 ADMINISTRATION OF THE CONTRACT
GC 2.1 AUTHORITY OF THE CO:\'SULTANT
2.1.1 The Consultant will have authority to act on behalf of the Owner only to the extent provided in the Contract
Documents, unless otherwise modified by written agreement as provided in paragraph 2.1.2.
2.1.2 The duties, responsibilities, and limitations of authority of the Consultant as set forth in the Contract
Documents shall be modified or extended only with the \vritten consent of the Owner, the Contractor, and the
Consultant.
2.1.3 If the Consultant's employment is terminated, the Owner shall immediately appoint or reappoint a Consultant
against whom the Contractor makes no reasonable objection and whose status under the Contract Documents
shall be that of the fanner Consultant.
eeDe 2 - 1994 File 007 I 2
10
Thi,,- con/rod iJ prVleded by Copyrigh/_ Ule r:/a C('DC 2 documen/ nOI comaining a (TDC 2 copyrighl .l'eal mn.\"lilU/e.\' an infringement (!f ClJpyrigh/. Only .Iign Ihis
conlra('1 ijlhe d(X7lmenl ('()l'er page hear" u CC'DC 2 mpyrighl seal/() rkmomtrale Ihal il i.1 in/ended by Ihe portie.1 /n he an occurOle and unomended liersion nfCCD(' 2
1994 except to the ex/ent tho! any a/feraliom;, add/lions 01 modijicaliom, (In; Jelforth in supplemen/ury condit/om;
GC 2.2 ROLE OF THE CONSULTANT
2.2.1 The Consultant will provide administration of the Contract as described in the Contract Documents during
construction until issuance of the final certificate for payment, and subject to GC 2.1 - AUTHORITY OF THE
CONSULT ANT and with the Chimer's concurrence, from time to time until the completion of any correction of
defects as provided in p3mgraph 12.3.30)-'(;(' 12..\ \VARRA:\'T"{,
2.2.2 The Consultant will visit the Place of the Work at intervals appropriate to the progress of construction to
become familiar with the progress and quality of the work and to determine if the Work is proceeding in
general conformity with the Contract Documents.
2.2.3 If the (fivner and the Consultant agree, the Consultant will provide at the Place of the Work, onc or more
project representatives to assist in carrying out the Consultant's responsibilities. The duties, responsibilities,
and limitations of authority of such project representatives shall be as set forth in writing to the Contractor.
2.2.4 Based on the Consultant's observations and evaluation of the Contractor's applications for payment, the
Consultant will determine the amounts owing to the Contractor under the Contract and will issue certificates
for payment as provided in Article /\-:) of the Agreement - PAYMENT, (iC 5.3 .. PRO(iRESS Pi\ yrvlFN'L
and GC 5.' . Fi"AI. PAYMI.5JT.
2.2.5 The Consultant will not be responsible for and will not have control, charge, or supervision of construction
means, methods, techniques, sequences, or procedures, or for safety precautions and programs required in
connection with the Work in accordance with the applicable construction safety legislation, other regulations, or
general construction practice. The Consultant will not be responsible for the Contractor's failure to carry out
the Work in accordance with the Contract Documents. The Consultant will not have control over, charge of, or
be responsible for the acts or omissions of the Contractor, Subcontractors, Suppliers, or their agents,
employees, or any other persons performing portions of the 'York.
2.2.6 The Consultant will be, in the first instance, the interpreter of the requirements of the Contract Documents and
shall make findings as to the perfonnance thereunder by both parties to the Contract, except with respect to
CC 5. [ - FlNANClNG I\:FOR\lATKf\ RIJJL:IRED (JF THt O\\-'"<L-.R. Interpretations and findings of the
Consultant shall be consistent with the intent of the Contract Documents. When making such interpretations
and findings the Consultant \vill not sho\v partiality to either the OHmer or the Contractor.
2.2.7 Claims, disputes, and other matters in question relating to the performance of the Work or the interpretation of
the Contract Documents, except for (ie 5,1 - F!Ni\NCIN(j fNFOR\-IATHOIXREQUIRE:D OF THE OWNER,
shall be referred initially to the Consultant by notice in 'Miting given to the Consultant and to the other party
for the Consultant's interpretation and finding which will be given by notice in \Vfiting to the parties within a
reasonable time.
2.2.8 The Consultant will have authority to reject work which in the Consultant's opinion does not confonn to the
requirements of the Contract Documents. \Vhenever the Consultant considers it necessary or advisable, the
Consultant will have authority to require inspection or testing of work, whether or not such work is fabricated,
installed, or completed. However, neither the authority of the Consultant to act nOf any decision either to
exercise or not to exercise such authority shall give rise to any duty or responsibility of the Consultant to the
Contractor, Subcontractors, Suppliers, or their agents, employees, or other persons performing any of the
Work.
2.2.9 During the progress of the W01* the Consultant will furnish Supplemental Instructions to the Contractor \Vith
reasonable promptness or in accordance with a schedule for such instructions agreed to by the Consultant and
the Contractor.
2.2.10 The Consultant will review and take appropriate action upon such Contractor's submittals as shop drawings,
Product data, and samples, as provided in the Contract Documents.
eeDe 2 .1994 File 00712
11
This contract is pm/ected hy Copyright U\'e uta CeDC 2 drl(:umen/ nm comaining a CCOC 2 copyright seal com-(i/Ules an infringement olCopyrigfn Only ,\ign this
comroC! iflhe document cover page hear,I' a CCIX~ 2 copyright ,fear 10 demons/rOle thai il is in/ended hy Ihe parties /() he an accurate and unamended l'erIion ofCCrx' 2
1994 e.xcept to the. extent t/wl any ultera/ions. additions or modijications are sel.lvrth in supplemenlwy conditiom'.
2.2.11 The Consultant will prepare Change Orders and Change Directives as provided in (;C (::2 ()L\NC;r
ORTJER and (iC 6J (TL\N(jj:~Djj<LC'rrVE-.
2.2.12 The Consultant will conduct reviews of the Work to determine the date of Substantial Performance of the
Work as provided in UU SA - SIIBSIA\-1 rAt PEEFORMANUE OF TilE WORK_
2.2.13 All certificates issued by the Consultant shall be to the best of the Consultant's knowledge, information, and
belief. By issuing any certificate, the Consultant does not guarantee the Work is correct or complete.
2.2.14 The Consultant will receive and review written warranties and related documents required by the Contract and
provided by the Contractor and will fOf\vard such warranties and documents to the Owner for the OI1-ner's
acceptance.
GC 2.3 REVIEW AND INSPECTION OF THE WORK
2.3.1 The Owner and the Consultant shall have access to the Work at all times. The Contractor shall provide
sufficient, safe, and proper facilities at all times for the review of the Work by the Consultant and the inspection
of the Work by authorized agencies. Ifparts of the Work are in preparation at locations other than the Place of
the Work, the OI1.ner and the Consultant shall be given access to such work whenever it is in progress.
2.3.2 If work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultants
instructions, or the laws or ordinances of the Place of the Work, the Contractor shall give the Consultant
reasonable notice of when the work \1,0111 be ready for reviC\v and inspection. The Contractor shall arrange for
and shall give the Consultant reasonable notice of the date and time of inspections by other authorities.
2.3.3 The Contractor shall furnish promptly to the Consultant N-'O copies of certificates and inspection reports
relating to the Work.
2.3.4 If the Contractor covers, or permits to be covered, work that has been designated for special tests, inspections,
or approvals before such special tests, inspections, or approvals are made, given or completed, the Contractor
shall, if so directed, uncover such work, have the inspections or tests satisfactorily completed, and make good
covering work at the ContractmJs expense.
2.3.5 The Consultant may order any portion or portions of the Work to be examined to confirm that such work is in
accordance with the requirements of the Contract Documents. If the work is not in accordance with the
requirements of the Contract Documents, the Contractor shall correct the work and pay the cost of
examination and correction. If the work is in accordance with the requirements of the Contract Documents, the
(J\Amer shall pay the cost of examination and restoration.
GC 2.4 DEFECTIVE WORK
2.4.1 The Contractor shall promptly remove from the Place of the Work and replace or re-execute defective work
that has been rejected by the Consultant as failing to conform to the Contract Documents whether or not the
defective work has been incorporated in the Work and whether or not the defect is the result of poor
workmanship, use of defective products, or damage through carelessness or other act or omission of the
Contractor.
2.4.2 The Contractor shall make good promptly other contractors' work destroyed or damaged by such removals or
replacements at the Contractor's expense.
2.4.3 If in the opinion of the Consultant it is not expedient to correct defective work or work not performed as
provided in the Contract Documents, the Owner may deduct from the amount otherwise due to the Contractor
the difference in value between the work as performed and that called for by the Contract Documents. If the
eeDe 2 - 1994 File 00712
12
Th~I' contra,'1 i,I' protec/ed by Copyright. (he ala CCDC 2 doclimenl nOI conUlining a CeDe 2 cofJ)-'rIglll s(!ol CO!l.l'IJlules an infringemen/ 1!/CopJ'righl. Only \"ign Ihi\"
w!llracllfthe documem COWl' page bear.I' a CCDe 2 wpyrigh/ .Iea/lo demon!,-Irale 1101-11 il iJ inlended by Ihe parti(!.I' 10 be 011 acr'urale ond unamended wr.\"ion o!"CCDC 2-
1994 exceptIO the exlent 11001 anyal/erations. additions or modifications are set/orih in supp{ementar~' condilions
Owner and the Contractor do not agree on the difference in value, they shall refer the matter to the Consultant
for a determination.
PART 3 EXECUTION OF THE WORK
GC 3.1 CONTROL OF THE WORK
3.1.1 The Contractor shall have total control of the Work and shall effectively direct and supervise the Work so as to
ensure conformity ,vith the Contract Documents.
3.1.2 The Contractor shall be solely responsible for construction means, methods, techniques, sequences, and
procedures and for co-ordinating the various parts of the Work under the Contract.
GC 3.2 CONSTRUCTION BY OWNER OR OTHER CONTRACTORS
3.2.1 The Owner reserves the right to award separate contracts in connection with other parts of the Project to other
contractors and to perform work with ovm forces.
3.2.2 \Vhen separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's
ovm forces, the Owner shall:
.1 provide for the co-ordination of the activities and work of other contractors and Owner's own forces with
the Work of the Contract;
.2 assume overall responsibility for compliance with the applicable health and construction safety legislation
at the Place of the Work;
.3 enter into separate contracts \vith other contractors under conditions of contract which are compatible with
the conditions of the Contract;
.4 ensure that insurance coverage is provided to the same requirements as are called for in erC 11 1
fNSUI;:ANCr: and co-ordinate such insurance with the insurance coverage of the Contractor as it affects
the Work; and
.5 take all reasonable precautions to avoid labour disputes or other disputes on the Project arising from the
work of other contractors or the Owner's own forces.
3.2.3 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's
own forces, the Contractor shall:
.1 afford the (hvner and other contractors reasonable opportunity to introduce and store their products and
use their construction machinery and equipment to execute their work;
.2 co-ordinate and schedule the Work with the work of other contractors and Owner's own forces and connect
as specified or shown in the Contract Documents;
.3 participate with other contractors and the Owner in reviewing their construction schedules when directed
to do so; and
.4 where part of the Work is affected by or depends upon for its proper execution the work of other
contractors or Owner's own forces, promptly report to the Consultant in \-vriting and prior to proceeding
with that part of the Work, any apparent deficiencies in such work.
CCDC2 -1994File00712
13
Thi,l contract is prorecled by Copyright, U\"e of a CCLX' 2 documenl nol conlaining a CCDe 2 copyrighl ,wm! cum'lilule,I' an infringement a/Copyright OnIY,)'lgn Ihis
conlrod i{the dncumenl cover page bears a CCOC 2 copyrighl sea/lo demonslmle Ihol il is inlended by Ihe panies 10 be on accurale and unamended version ofCCJX' 2-
1994 eu:ept to Ihe extent Ihm any alterations, mlditions or modllication!>' are 8'el!urlh in supp!emenlory conditions
Failure by the Contractor to so report shall invalidate any claims against the Owner by reason of the
deficiencies in the work of other contractors or Owner's own forces except those deficiencies not then
reasonably discoverable.
3.2.4 Where a change in the Work is required as a result of the co-ordination and connection of the work of other
contractors or Owner's own forces with the Work, the changes shall be authorized and valued as provided in
cre' 6_1 ('jJANC;rS, (iC 6.2 ClJi\O'<C.1E C)RI)[R, and (I(' ':;_:' CIL\\(jL: DiH i;(:T1VF.
3.2.5 Claims, disputes, and other matters in question between the Contractor and other contractors shall be dealt with
as provided in Pmi R of dK' General ConditlPH;'; " DlSPUTr~ RL:SOLUTHJN provided the other contractors
have reciprocal obligations. The Contractor shall be deemed to have consented to arbitration of any dispute
with any other contractor whose contract with the Owners contains a similar agreement to arbitrate.
GC 3.3 TEMPORARY SUPPORTS, STRUCTURES, AND FACILITIES
3.3.1 The Contractor shall have the sole responsibility for the design, erection, operation, maintenance, and removal
of temporary supports, structures, and facilities and the design and execution of constmction methods required
in their use.
3.3.2 The Contractor shall engage and pay for registered professional engineering personnel skilled in the
appropriate disciplines to perform those functions referred to in paragraph 3.3.1 where required by law or by
the Contract Documents and in all cases where such temporary supports, structures, and facilities and their
method of construction are of such a nature that professional engineering skill is required to produce safe and
satisfactory results.
3.3.3 Notwithstanding the provisions of GC 3.1 - CONTROL OF THE WORK, paragraph 3.3.1, and paragraph
3.3.2 or provisions to the contrary elsewhere in the Contract Documents where such Contract Documents
include designs for temporary supports, structures, and facilities or specify a method of construction in whole
or in part, such facilities and methods shall be considered to be part of the design of the Work and the
Contractor shall not be held responsible for that part of the design or the specified method of construction.
The Contractor shall, however, be responsible for the execution of such design or specified method of
construction in the same manner as for the execution of the Work.
GC 3.4 DOCUMENT REVIEW
3.4.1 The Contractor shall review the Contract Documents and shall report promptly to the Consultant any error,
inconsistency, or omission the Contractor may discover. Such review by the Contractor shall be to the best of
the Contractor's knowledge, information, and belief and in making such review the Contractor does not
assume any responsibility to the OI1-'ner or the Consultant for the accuracy of the review. The Contractor shall
not be liable for damage or costs resulting from such errors, inconsistencies, or omissions in the Contract
Documents, which the Contractor did not discover. If the Contractor does discover any error, inconsistency,
or omission in the Contract Documents, the Contractor shall not proceed with the work affected until the
Contractor has received corrected or missing infol1l1ation from the Consultant.
GC 3.5 CONSTRUCTION SCHEDULE
3.5.1 The Contractor shall:
.1 prepare and submit to the Ovmer and the Consultant prior to the first application for payment, a
construction schedule that indicates the timing of the major activities of the Work and provides sufficient
detail of the critical events and their inter-relationship to demonstrate the Work will be performed In
conformity with the Contract Time;
eeDe 2 - 1994 File 00712
14
Fhi.1 wntraclls prolected by Copyr(ghf, Uxe afa CC1X~ 2 documenl mJl cOnlainlng a CCDe 2 copyrighl ,\'(:o{ wn,j'IUUle.\' un Inji"ingemml afCopyrlght. On!y slgnlhi,
cunfracl i/lhe documenl cover pug.: bear.,' a CCOC 2 copyrighl ~ea{ /0 demons/rOle IhO! il is in/ended by Ihe parlie.\" /0 be on acwra/e and unamended ver,lion olCe/X.' 2--
1994 =epllo Ihe exlenllha/ any alteraliom, additionl" or modificalian.l" are ;'el!iJrlh in ~'upplemenlary condiliom
.2 monitor the progress of the Work relative to the construction schedule and update the schedule on a
monthly basis or as stipulated by the Contract Documents; and
.3 advise the Consultant of any revisions required to the schedule as the result of extensions of the Contract
Time as provided in PJrl6 of the C!i:nerJJ (\)f[Cblions (}I/\'\CtF'S IN TilL \VURl\..
GC 3.6 CONSTRUCTION SAFETY
3.6.1 Subject to l.LL2 GfCiC 1.2 {'ONS"T RtiC T1D:-- B\' O\\'\ER OR OTH[R CC!\;'fiL\C'TORS, the
Contractor shall be solely responsible for construction safety at the Place of the Work and for compliance with
the rules, regulations, and practices required by the applicable construction health and safety legislation and
shall be responsible for initiating, maintaining, and supervising all safety precautions and programs in
connection with the perfonnance of the Work.
GC 3.7 SUPERVISOR
3.7.1 The Contractor shall employ a competent supervisor and necessary assistants who shall be in attendance at the
Place of the Work while work is being performed. The supervisor shall not be changed except for valid reason.
3.7.2 The supervisor shall represent the Contractor at the Place of the Work and notices and instructions given to the
supervisor by the Consultant shall be held to have been received by the Contractor.
GC 3.8 SUBCONTRACTORS AND SUPPLIERS
3.8.1 The Contractor shall preserve and protect the tights of the parties under the Contract with respect to work to
be performed under subcontract, and shall:
.1 enter into contracts or Mitten agreements with Subcontractors and Suppliers to require them to perform
their work as provided in the Contract Documents;
.2 incorporate the tenus and conditions of the Contract Documents into all contracts or written agreements
with Subcontractors and Suppliers; and
.3 be as fully responsible to the CJovvner for acts and omissions of Subcontractors, Suppliers, and of persons
directly or indirectly employed by them as for acts and omissions of persons directly employed by the
Contractor.
3.8.2 The Contractor shall indicate in writing, at the request of the Cfivner, tho:;e Subcontractors or Suppliers whose
bids have been received by the Contractor which the Contractor \vould be prepared to accept for the
performance of a portion of the Work. Should the Owner not object before signing the Contract, the
Contractor shall employ those Subcontractors or Suppliers so identified by the Contractor in writing for the
performance of that portion of the Work to which their bid applies.
3.8.3 The Owner may, for reasonable cause, at any time before the OVI/ner has signed the Contract, object to the use
of a proposed Subcontractor or Supplier and require the Contractor to employ one of the other subcontract
bidders.
3.8.4 If the Ovmer requires the Contractor to change a proposed Subcontractor or Supplier, the Contract Price and
Contract Time shall be adjusted by the differences occasioned by such required change.
3.8.5 The Contractor shall not be required to employ as a Subcontractor or Supplier, a person or finn to whom the
Contractor may reasonably object.
ceDe 2 - 1994 File 00712
15
Thi.\. contract is protecled by CopyriKhL [}I"{! ofa CCIX 2 do(:umenl not cOn/aining a CC[x' 2 copyrighl .Ieal conslitU/e.\ an infringement of Copyright Only sign this
cOn/ract iflhe documem COVt'f page bears a CCDe 2 ,.opyright sea/IV demons/rale (hal il L\. imended hy the par/ies /0 be an accurate and unamended I"er~'ion ofCCDC 2
1994 creep' to the extent thai any allerations, addilions or modifications are seiforth in supplementw),. cundilions.
3.8.6 The Oltmer, through the Consultant, may provide to a Subcontractor or Supplier information as to the
percentage of the Subcontractor's or Supplier's work which has been certified for payment.
GC 3.9 LABOUR AND PRODUCTS
3.9.1 The Contractor shall provide and pay for labour, Products, tools, construction machinery and equipment,
water, heat, light, power, transportation, and other facilities and services necessary for the performance of the
Work in accordance with the Contract.
3.9.2 Products provided shall be new. Products which are not specified shall be of a quality consistent with those
specified and their use acceptable to the Consultant.
3.9.3 The Contractor shall maintain good order and discipline among the Contractor's employees engaged on the
Work and shall not employ on the Work anyone not skilled in the tasks assigned.
GC 3.10 DOCUMENTS AT THE SITE
3.10.1 The Contractor shall keep one copy of current Contract Documents, submittals, reports, and records of
meetings at the Place o/the Work, in good order and available to the Owner and the Consultant.
GC 3.11 SHOP DRAWINGS
3.11.1 Shop drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures, Product, and
other data which the Contractor provides to illustrate details of a portion of the Work.
3.11.2 The Contractor shall provide shop drawings as described in the Contract Documents or as the Consultant may
reasonably request.
3.11.3 The Contractor shall review all shop drawings prior to submission to the Consultant. The Contractor
represents by this review that: the Contractor has determined and verified all field measurements and field
construction conditions, or will do so; Product requirements; catalogue numbers; and similar data and that the
Contractor has checked and co-ordinated each shop drawing \vith the requirements of the Work and of the
Contract Documents. The Contractor shall confinn this review of each shop drawing by stamp, date, and
signature of the person responsible. At the time of submission the Contractor shall notify the Consultant in
'Writing of any deviations in the shop drawings from the requirements of the Contract Documents.
3.11.4 The Contractor shall submit shop drawings to the Consultant to review in orderly sequence and sufficiently in
advance so as to cause no delay in the Work or in the work of other contractors. Upon request of the
Contractor or the Consultant, they jointly shall prepare a schedule of the dates for submission and return of
shop drawings. Shop drawings which require approval of any legally constituted authority having jurisdiction
shall be submitted to such authority by the Contractor for approval.
3.11.5 The Contractor shall submit shop drawings in the form specified or as the Consultant may direct. The
Consultant will review and return shop drawings in accordance with the schedule agreed upon, or othelVr'ise
with reasonable promptness so as to cause no delay. The Consultants review is for conformity to the design
concept and for general arrangement only. The Consultant's review shall not relieve the Contractor of
responsibility for errors or omissions in the shop drawings or for meeting all requirements of the Contract
Documents unless the Consultant expressly notes the acceptance of a deviation on the shop drawings.
3.11.6 Upon the Consultant's request, the Contractor shall revise and resubmit shop drawings which the Consultant
rejects as inconsistent with the Contract Documents unless othef\vise directed by the Consultant. The
Contractor shall notify the Consultant in 'Writing of any revisions to the resubmission other than those
requested by the Consultant.
eeDe 2 -1994 File 00712
16
This contracl is prOlecled by CopyrighL Use oIa CCDC 2 document nol wnlaining a ceDe 2 copyrighl ,'eol con.l'lilule.\ an injhngemenl ojCflpyriKhr. Only .\iKn Ihis
comraCI (!the documenl C'(Jl'er page bean a CClX~ 2 copyrighl :ieallO demon.\lrale (hal II is in/ended by the par/ie.l1O be an accurale and unamended l"a,)'lOn (:if e("IX' 2--
/994 creep! 10 Ihe exlen/ thai any ai/era/10m'. additions or modijicalions are setjorlh in supplemenrary com/ilion.)'.
GC 3.12 USE OF THE WORK
3.12.1 The Contractor shall confine construction machinery and equipment, storage of Products, and operations of
employees to limits indicated by laws, ordinances, permits, or the Contract Documents and shall not
unreasonably encumber the Work with Products.
3.12.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will
endanger the safety of the Work.
GC 3.13 CUTTING AND REMEDIAL WORK
3.13.1 The Contractor shall do the cutting and remedial work required to make the several parts of the Work come
together properly.
3.13.2 The Contractor shall co-ordinate the Work to ensure that this requirement is kept to a minimum.
3.13.3 Should the Owner, the Consultant, other contractors or anyone employed by them be responsible for ill-timed
work necessitating cutting or remedial work to be performed, the cost of such cutting or remedial work shall be
valued as provided in (ie: 6.1 Cl-{;\NGES, eiC 6,2 c'lL\\:\iC and GC 6J C'}[i\NGC
DlRF\TIVE.
3.13.4 Cutting and remedial work shall be performed by specialists familiar with the Products affected and shall be
performed in a manner to neither damage nor endanger the Work.
GC 3.14 CLEANUP
3.14.1 The Contractor shall maintain the Work in a tidy condition and free from thc accumulation of waste products
and debris, other than that caused by thc Owner, other contractors or their employees.
3.14.2 The Contractor shall remove waste products and debris, other than that resulting from the work of the Owner,
other contractors or their employees, and shall leave the Work clean and suitable for occupancy by the Owner
before attainment of Substantial Performance of the Work. The Contractor shall remove products, tools,
construction machinery, and equipment not required for the performance of the remaining work.
3.14.3 Prior to application for the final certificate for payment, the Contractor shall remove products, tools,
construction machinery and equipment, and waste products and debris, other than that resulting from the work
of the Ovvner, other contractors or their employees.
PART 4 ALLOWANCES
GC 4.1 CASH ALLOW A:'olCES
4.1.1 The Contract Price includes cash allowances stated in the Contract Documents, which allowances shall be
expended as the Owner directs through the Consultant.
4.1.2 Cash allowances cover the net cost to the Contractor of services, Products, construction machinery and
equipment, freight, unloading, handling, storage, installation, and other authorized expenses incurred in
performing the work stipulated under the cash allowances but do not include any Value Added Taxes payable
by the Owner to the Contractor.
ceDe 2 - 1994 File 00712
17
T/li_\' eontrac/ is prOlecred by Copyright U,'e ofa CCOC 2 drx7Jmen/ nol moraining 0 CClX 2 copyrighl .Ieal con.lllIlIIes an infringemenl of Copy righi, Only sign Ihi,,'
eon/racl il1he doeumenr cover page bear.1 a CCfX' 2 COPYrlKhl seaf 10 demons/rUle Ihul il '" il1/!:!IIled by Ihe par/Ie.' /0 hI' UI1 ac'c'urale and u/"lffN:nded ,'er,wm o{CCIX' 2
1994 I'xcepllo the exlem Ihal airy-' al/era/iom;. additions or modijicalions are setjorlll in supplemlmlary nmdilians.
4.1.3 The Contract Price, and not the cash allowances, includes the Contractor's overhead and profit in connection
with such cash allowances.
4.1.4 Where costs under a cash allowance exceed the amount of the allowance, the Contractor shall be compensated
for any excess incurred and substantiated plus an amount for overhead and profit as set out in the Contract
Documents.
4.1.5 The Contract Price shall be adjusted by Change Order to provide for any difference between the actual cost
and each cash allowance.
4.1.6 The value of the work performed under a cash allowance is eligible to be indudcd in progress payments.
4.1.7 The Contractor and the Consultant shall jointly prepare a schedule that shows when the Consultant and Owner
must authorize ordering of items called for under cash allowances to avoid delaying the progress of the Work.
GC 4.2 CONTINGENCY ALLOWANCE
4.2.1 The Contract Price includes the contingency allowance, if any, stated in the Contract Documents.
4.2.2 Expenditures under the contingency allowance shall be authorized and valued as provided in (ie' ')
GC {),2 CTJANCiE ORDER, and GC: (d ~ CH:\N(;E DlREJ.TI\;, E.
4.2.3 The Contract Price shall be adjusted by Change Order to provide for any difference between the expenditures
authorized under paragraph 4.2.2 and the contingency allowance.
PART 5 PAYMENT
GC 5.1 FINANCING INFORMATION REQUIRED OF THE OWNER
5.1.1 The Owner shall, at the request of the Contractor, prior to execution of the Agreement, and/or promptly ITom
time to time thereafter, furnish to the Contractor reasonable evidence that financial arrangements have been
made to fulfill the Owner's obligations under the Contract.
5.1.2 The Owner shall notify the Contractor in writing of any material change in the Owner's financial arrangements
during the perfonnancc of the Contract.
GC 5.2 APPLICATIONS FOR PROGRESS PAYMENT
5.2.1 Applications for payment on account as provided in Article A-S of the Agreement . PAYMENT may be made
monthly as the Work progresses.
5.2.2 Applications for payment shall be dated the last day of the agreed monthly payment period and the amount
claimed shall be for the value, proportionate to the amount of the Contract, of work performed and Products
delivered to the Place of the Work at that date.
5.2.3 The Contractor shall submit to the Consultant, at least 14 days before the first application for payment, a
schedule of values for the parts of the Work, aggregating the total amount of the Contract Price, so as to
facilitate evaluation of applications for payment.
CCDC2-1994File00712 18
lhis mntract is protected by ('opyright. UI'e ora eelX.-' 2 do{."Umenl no! mnloimng a CClX' 2 mpyrighl seal mnslilule,I' an inji"ingemenl orCopyngh/, Only.\'lgn Ihis
con/roc( if'lhe oocl./menl co\'er page bears (I ('C1X~ 2 copyright .I'ealto demon,\'Iro/e Ihm il is in/ended by Ihe panies 10 be an (I("('urale and unamended verI/on ojCCIX' 2
1994 excepllo Ihe o1en/ Iha/ arry ai/era/ions. addiJions or modifications are set/ilr/h in supplementary conditions
5.2.4 The schedule of values shall be made out in such form and supported by such evidence as the Consultant may
reasonably direct and when accepted by the Consultant, shaH be used as the basis for applications for payment,
unless it is found to be in error.
5.2.5 The Contractor shall include a statement based on the schedule of values \Vith each application for payment.
5.2.6 Claims for Products delivered to the Place of the Work but not yet incorporated into the Work shall be
supported by such evidence as the Consultant may reasonably require to establish the value and delivery of the
Products.
GC 5.3 PROGRESS PAYMENT
5.3.1 Thc Consultant \ViII issue to the Owner, no later than 10 days after the receipt of an application for payment
from the Contractor submitted in accordance with GC 5.2 . APPLTCA nONS FOR PROGRESS PAYMENT.
a certificate for payment in the amount applied for or in such other amount as the Consultant determines to be
properly due. If the Consultant amends the application, the Consultant will promptly notify the Contractor in
writing giving reasons for the amendment.
5.3.2 The Owner shall make payment to the Contractor on account as provided in Article A-5 of the Agreement -
P A YrvlENT no later than 5 days after the date of a certificate for payment issued by the Consultant.
GC 5.4 SUBSTANTIAL PERFORMANCE OF THE WORK
5.4.1 When the Contractor considers that the Work is substantially performed, or if permitted by the lien legislation
applicable to the Place of the Work a designated portion thereof which the Owner agrees to accept separately is
substantially performed, the Contractor shall prepare and submit to the Consultant a comprehensive list of
items to be completed or corrected and apply for a review by the Consultant to establish Substantial
Peiformance of the Work or substantial performance of the designated portion of the Work. Failure to include
an item on the list does not alter the responsibility of the Contractor to complete the Contract.
5.4.2 No later than 10 days after the receipt of the Contractor's list and application, the Consultant will review the
Work to verify the validity of the application, and no later than 7 days after completing the review, \ViII notify
the Contractor whether the Work or the designated portion of the Work is substantially perrormed.
5.4.3 The Consultant shall state the date of Substantial Performance of the Work or designated portion of the Work
in a certificate.
5.4.4 Immediately following the issuance of the certificate of Substantial Performance of the Work, the Contractor,
in consultation with the Consultant, will establish a reasonable date for finishing the Work.
GC 5.5 PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE WORK
5.5.1 After the issuance of the certificate of Substantial Performance of the Work, the Contractor shall:
.1 submit an application for payment of the holdback amount,
.2 submit a sworn statement that all accounts for labour, subcontracts, Products, construction machinery
and equipment, and other indebtedness which may have been incurred by the Contractor in the
Substantial Performance of the Work and for which the Owner might in any way bc held responsible
have been paid in full, except for amounts properly retained as a holdback or as an identified amount
in dispute.
ceDe 2.1994 File 00712
19
Ih!:~ con/rad !,\. protec/ed by Copyright. Use ofa CClX' 2 doc Ilmenl nO! conlllining a CCJX~ 2 copyrighl .\"I!al CI1l1.1'lltllle.\. (fr/ infringemen/ ofCopyrighr. Only sign Ihil.
mntracl/rlhe documenl cover page bear.l. a CeDC 2 capyrighl .~eal to demonstrate Ihal il is intended by Ihe parlin to be an acy-urale and unamended version o/CCfX~ 2-
1994 except /a Ihe exlent Ihal any alterations, additions or modifications are setforth in .\"Upplementary conditions
5.5.2 After the receipt of an application for payment from the Contractor and the sworn statement as provided in
paragraph 5.5.1, the Consultant will issue a certificate for payment of the holdback amount.
5.5.3 Where the holdback amount has not been placed in a separate holdback account, the Owner shall, 10 days prior
to the expiry of the holdback period stipulated in the lien legislation applicable to the Place of the Work, place
the holdback amount in a bank account in the joint names of the Ol1-ner and the Contractor.
5.5.4 The holdback amount authorized by the certificate for payment of the holdback amount is due and payable on
the day following the expiration of the holdback period stipulated in the lien legislation applicable to the Place
of the Work. Where lien legislation does not exist or apply, the holdback amount shall be due and payable in
accordance with other legislation, industry practice, or provisions which may be agreed to between the parties.
The Ol-imer may retain out of the holdback amount any sums required by law to satisfy any liens against the
Work or, if permitted by the lien legislation applicable to the Place of the Work, other third party monetary
claims against the Contractor which are enforceable against the Owner.
GC 5.6 PROGRESSIVE RELEASE OF HOLDBACK
5.6.1 Where legislation pemrits and where, upon application by the Contractor, the Consultant has certified that the
work of a Subcontractor or Supplier has been performed prior to Substantial Performance of the Work, the
Owner shall pay the Contractor the holdback amount retained for such subcontract work, or the Products
supplied by such Supplier, on the day following the expiration ofthe holdback period for such work stipulated
in the lien legislation applicable to the Place of the Work.
5.6.2 Notwithstanding the provisions of the preceding paragraph, and notwithstanding the wording of such
certificates, the Contractor shall ensure that such subcontract work or Products is protected pending the
issuance of a final certificate for payment and be responsible for the correction of defects or work not
performed regardless of whether or not such was apparent when such certificates were issued.
GC 5.7 FINAL PAYMENT
5.7.1 When the Contractor considers that the Work is completed, the Contractor shall submit an application for final
payment.
5.7.2 The Consultant will, no later than 10 days after the receipt of an application from the Contractor for final
payment, review the Work to verify the validity of the application. The Consultant will, no later than 7 days
after reviewing the Work, notify the Contractor that the application is valid or give reasons why it is not valid.
5.7.3 'When the Consultant finds the Contractor's application for final payment valid, the Consultant will issue a
final certificate for payment.
5.7.4 Subject to the provision of H),U of C.iC lOA WORKERS' COI'vlFENSAT10N. and any lien
legislation applicable to the Place of the Work, the Owner shall, no later than 5 days after the issuance ofa final
certificate for payment, pay the Contractor as provided in Article A-) of the Agreement - PAYMENT.
GC 5.8 WITHHOLDING OF PAYME:"T
5.8.1 If because of climatic or other conditions reasonably beyond the control of the Contractor, there are items of
work that cannot be perfonned, payment in full for that portion of the Work which has been performed as
certified by the Consultant shall not be withheld or delayed by the Ol'mer on account thereof, but the Owner
may withhold, Wltil the remaining portion of the Work is finished, only such an amount that the Consultant
detennines is sufficient and reasonable to cover the cost of perfonning such remaining work.
ceDe 2 - 1994 File 00712
20
Thi~ con/rac! is prOlecled by Copyrighr UI-e a/a CC[X' 2 dix/Jmell/ nol wnlOlninRa CCDC 2 wpyrigh/.leul um.\li/Ule.l an injTin~menl of'Cof!yrigh/. Only ,1'lgn Ihi_\'
contrac/ iithe do('umenl cover page bear.1 fJ CCIX~ 2 copyr(gh/ sea/Iv demon.llrale Ihal 1/ i.I' irllended by /he parlie,I' to be un un'urale and unanwndi'd version i!f(X:f)(~ 2 -
1994 e.:rcepl to Ihe. ex/en/lhal any altera/ions. ack/iII'ons or modijicatiom- are .I'elfarlh in supplementary conditions
GC 5.9 NON-CO:"lFORMING WORK
5.9.1 No payment by the Owner under the Contract nor partial or entire use or occupancy of the Work by the Owner
shall constitute an acceptance of any portion of the Work or Products which are not in accordance with the
requirements of the Contract Documents.
PART 6 CHANGES IN THE WORK
GC 6.1 CHANGES
6.1.1 The Owner, through the Consultant, without invalidating the Contract, may make changes in the Work
consisting of additions, deletions, or other revisions to the Work by Change Order or Change Directive.
6.1.2 The Contractor shall not perform a change in the Work without a Change Order or a Change Directive.
GC 6.2 CHANGE ORDER
6.2.1 When a change in the Work is proposed or required, the Consultant shall provide a notice describing the
proposed change in the Work to the Contractor. The Contractor shall present, in a fonn acceptable to the
Consultant, a method of adjustment or an amount of adjustment for the Contract Price, if any, and the
adjustment in the Contract Time, if any, for the proposed change in the Work.
6.2.2 When the Owner and Contractor agree to the adjustments in the Contract Price and Contract Time or to the
method to be used to determine the adjustments, such agreement shall be effective immediately and shall be
recorded in a Change Order, signed by Owner and Contractor. The value of the work performed as the result
of a Change Order shall be included in applications for progress payment.
GC 6.3 CHANGE DIRECTIVE
6.3.1 If the Owner requires the Contractor to proceed with a change in the Work prior to the Ovmer and the
Contractor agreeing upon the adjustment in Contract Price and Contract Time, the Ovmer, through thc
Consultant, shall issue a Change Directive.
6.3.2 Upon receipt of a Change Directive, the Contractor shall proceed promptly with the change in the Work. The
adjustment in the Contract Price for a change carried out by way of a Change Directive shall be determined on
the basis of the cost of expenditures and savings to perform the work attributable to the change. If a change in
the Work results in a net increase in the Contract Price, an allowance for overhead and profit shall be included.
6.3.3 If a change in the Work results in a net decrease in the Contract Price, the amount of the credit shall be the net
cost, without deduction for overhead or profit. \Vhen both additions and deletions covering related work or
substitutions are involved in a change in the Work, the allowance for overhead and profit shall be calculated on
the basis of the net increase, if any, \vith respect to that change in the Work.
6.3.4 The Contractor shall keep and present, in such form as the Consultant may require, an itemized accounting of
the cost of expenditures and savings referred to in paragraph 6.3.2 together with supporting data. The cost of
performing the work attributable to the Change Directive shall be limited to the actual cost of all of the
following:
.1 wages and benefits paid for labour in the direct employ of the Contractor under applicable collective
bargaining agreements, or under a salary or wage schedule agreed upon by the Owner and Contractor;
eeDe 2 -1994 File 00712 21
This contl'aCI i.l" protecled by Copyright. UH~ /Jfu CCIX' 2 dowment nol comaininf!; a ('('DC 2 copyr(r;h/ seal nJn.\"II/ule\' un infringemem a/Copyright. Only sign /his
conlraa if/he document caver page bears a ('ClX' 2 wpyrighl seal 10 demons/rale Iha! it is intended by Ihe parries 10 be an (lccurale and unamended ">'enioll o(CCFX-' 2
1994 excepllO the ,'Xtem that any alterations, addilions or modifiwtions are set/or/h in supplementary conditiolls
.2 salaries, wages, and benefits of the Contractor's office personnel engaged in a technical capacity and
other personnel at shops or on the road, engaged in expediting the production or transportation of
materials or equipment;
.3 contributions, assessments, or taxes incurred for such items as unemployment insurance, provincial health
insurance, workers' compensation, and Canada or Quebec Pension Plan, insofar as such cost is based on
wages, salaries, or other remuneration paid to employees of the Contractor and included in the cost of the
work as provided in paragraphs 6.3.4.1 and 6.3.4.2;
.4 travel and subsistence expenses of the Contractor's personnel described in paragraphs 6.3.4.1 and
6.3.4.2;
.5 the cost of all Products including cost of transportation thereof;
.6 the cost of materials, supplies, equipment, temporary services and facilities, and hand tools not owned by
the workers, including transportation and maintenance thereof, \vhich are consumed; and cost less salvage
value on such items used but not consumed, which remain the property of the Contractor;
.7 rental cost of all tools, machinery, and equipment, exclusive of hand tools, whether rented from or
provided by the Contractor or others, including installation, minor repairs and replacements, dismantling,
removal, transportation and delivery cost thereof;
.8 deposits lost;
.9 the amounts of all subcontracts;
.10 the cost of quality assurance such as independent inspection and testing services;
.11 charges levied by authorities having jurisdiction at the Place of the Work;
.12 royalties, patent license fees, and damages for infringement of patents and cost of defending suits therefor
subject always to the Contractors obligations to indenmify the Owner as provided in HJ.3, 1 rJt
GC 103 - PATENT
.13 any adjustment in premiwns for all bonds and insurance which the Contractor is required, by the
Contract Documents, to purchase and maintain;
.] 4 any adjustment in taxes and duties for which the Contractor is liable;
.15 charges for long distance telephone and facsimile conununications, courier services, expressage, and
petty cash items incurred;
.16 the cost of removal and disposal of waste products and debris;
.17 cost incurred due to emergencies affecting the safety of persons or property;
6.3.5 Pending detennination of the final amount of a Change Directive, the undisputed value of the work performed
as the result of a Change Directive is eligible to be included in progress payments.
6.3.6 lfthe Owner and Contractor do not agree on the proposed adjustment in the Contract Time or the method of
determining it, the adjustment shall be referred to the Consultant for determination.
6.3.7 lf at any time after the start of the work directed by a Change Directive, the Ovmer and the Contractor reach
agreement on the adjustment to the Contract Price and to the Contract Time, this agreement shall be recorded
in a Change Order signed by Owner and Contractor.
eeDe 2 - 1994 File 00712
22
This contracl i.1 proteeled by Copyright. [J~'e ora CCIX' 2 document nol conlaimng a CCOC 2 copyriglu .\"eo/ ('(Ins/ilule,I' an infringemenl of Copy rig hi OnZI- ,\'IJ?n Ihix
conlroc! if/he Joelfmenl cover page bears a ceDe 2 copyrighlseallo demonslrote /hal i/ ix intended by Ihe par/iex to be an a,\ urale and unamended !'en-ion ofCCIX~ 2
1994 exceptio the f';({entlhat any alterUlions, addiliom' or modljicolirms "re ~'e/farlh in suppll;mentury conditioll_I'
GC 6.4 CONCEALED OR UNKNOWN CONDITIONS
6.4.1 If the Owner or the Contractor discover conditions at the Place afthe Work which are:
.1 subsurface or othef\.Vise concealed physical conditions which existed before the commencement of the
Work which differ materially from those indicated in the Contract Documents; or
.2 physical conditions of a nature which differ materially from those ordinarily found to exist and generally
recognized as inherent in construction activities of the character provided for in the Contract Documents;
then the observing party shall notify the other party in writing before conditions are disturbed and in no event
later than 5 Working Days after first observance of the conditions.
6.4.2 The Consultant will promptly investigate such conditions and make a finding. If the finding is that the
conditions differ materially and this \-vould cause an increase or decrease in the Contractor's cost or time to
petform the Work, the Consultant, with the Owner's approval, shall issue appropriate instructions for a change
in the Work as provided in GC~ 6.:, - CI-JANCn: ORDEH or {it': (;,3 "CHANGE l>TR.ECTf\.rr..
6.4.3 If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change
in the Contract Price or the Contract Time is justified, the Consultant shall report the reasons for this finding to
the (hmer and the Contractor in writing.
GC 6.5 DELAYS
6.5.1 Tfthe Contractor is delayed in the petformance of the Work by an action or omission of the CJM.'ner, Consultant,
or anyone employed or engaged by them directly or indirectly, contrary to the provisions of the Contract
Documents, then the Contract Time shall be extended for such reasonable time as the Consultant may
recommend in consultation with the Contractor. The Contractor shall be reimbursed by the Owner for
reasonable costs incurred by the Contractor as the result of such delay.
6.5.2 If the Contractor is delayed in the performance of the Work by a stop work order issued by a court or other
public authority and providing that such order was not issued as the result of an act or fault of the Contractor or
any person employed or engaged by the Contractor directly or indirectly, then the Contract Time shall be
extended for such reasonable time as the Consultant may recommend in consultation with the Contractor. The
Contractor shall be reimbursed by the Owner for reasonable costs incurred by the Contractor as the result of
such delay.
6.5.3 If the Contractor is delayed in the performance of the Work by labour disputes, strikes, lock-outs (including
lock-outs decreed or recommended for its members by a recognized contractors' association, of which the
Contractor is a member or to which the Contractor is othef\vise bound), fire, unusual delay by common
carriers or unavoidable casualties, or without limit to any of the foregoing, by a cam,e beyond the Contractor's
control, then the Contract Time shall be extended for such reasonable time as the Consultant may recommend
in consultation with the Contractor. The extension of time shall not be less than the time lost as the result of
the event causing the delay, unless the Contractor agrees to a shorter extension. The Contractor shall not be
entitled to payment for costs incurred by such delays unless such delays result from actions by the OV'mer.
6.5.4 No extension shall be made for delay unless notice in \\!Titing of claim is given to the Consultant not later than
10 Working Days after the commencement of delay, providing however, that in the case of a continuing cause
of delay only one notice of claim shall be necessary.
6.5.5 Ifno schedule is made under ".2,9 ni'(]C.2,::, ROLE OrnrE CO\SULTANT, no claim for delay
shall be allowed because of failure of the Consultant to furnish instructions until 10 Working Days after
demand for such instructions has been made and not then, unless the claim is reasonable.
eeDe 2 - ]994 File 00712 23
This contract is prolected by Copyrighl Use oIo CC[[ 2 drl(71!r1em not nmwining 0 CC/X' 2 copyright .Ieal con:;rilUIr:.1 WI infi'ingement ofCopyrighi Only sifJl1 this
conlraci iflhe document cover fX'Ke hears a CeDe 2 copy'Wht xeaf 10 demrmslrate Ihat it i,I' inlended hy the parlie~ 10 be an aa:urare ilnd unamended version r~rCClX~ 2
/994 e.x;cept 10 Ihe ex/en/lhat any a/lcralium. addilions ur modificatiom are sel.lurlh in supplemrmlary conditions.
PART 7 DEFAULT NOTICE
GC 7.1 OWNER'S RIGHT TO PERFORM THE WORK, STOP THE WORK, OR TERMINATE THE
CONTRACT
7.1.1 If the Contractor should be adjudged bankrupt, or makes a general assignment for the benefit of creditors
because of the Contractor's insolvency, or if a receiver is appointed because of the Contractor's insolvency, the
Owner may, without prejudice to any other right or remedy the O\1-'ner may have, by giving the Contractor or
receiver or trustee in bankruptcy notice in writing, tenninate the Contract.
7.1.2 If the Contractor should neglect to prosecute the Work properly or otherwise fails to comply \Vith the
requirements of the Contract to a substantial degree and if the Consultant has given a written statement to the
Owner and Contractor that sufficient cause exists to justify such action, the Owner may, without prejudice to
any other right or remedy the OHmer may have, notify the Contractor in writing that the Contractor is in
default of the Contractor's contractual obligations and instruct the Contractor to correct the default in the 5
Working Days immediately following the receipt of such notice.
7.1.3 Tfthe default cannot be corrected in the 5 Working Days specified, the Contractor shall be in compliance with
the Owners instructions if the Contractor:
.1 commences the correction of the default within the specified time, and
.2 provides the ClIiI:ner \vith an acceptable schedule for such correction, and
.3 corrects the default in accordance with such schedule.
7.1.4 If the Contractor fails to correct the default in the time specified or subsequently agreed upon, without
prejudice to any other right or remedy the O~~mer may have, the OVI--ner may:
,I correct such default and deduct the cost thereof from any payment then or thereafter due the Contractor
provided the Consultant has certified such cost to the OVI-'ner and the Contractor, or
.2 tenninate the Contractor's right to continue with the Work in whole or in part or tenninate the Contract.
7,1.5 If the Owner terminates the Contractor's right to continue with the Work as provided in paragraphs 7,1 1 and
7.1.4, the Owner shall be entitled to:
.1 take possession of the Work and Products; utilize the construction machinery and equipment; subject to
the rights of third parties, finish the Work by whatever method the Owner may consider expedient, but
without undue delay or expense, and
.2 withhold further payment to the Contractor until a final certificate for payment is issued, and
.3 charge the Contractor the amount by which the full cost of finishing the Work as certified by the
Consultant, including compensation to the Consultant for the Consultant's additional services and a
reasonable allowance as detennined by the Consultant to cover the cost of corrections to work performed
by the Contractor that may be required under Ci(' 1 \\;\kRA'<rV exceeds the unpaid balance of the
Contract Price; however, if such cost of finishing the Work is less than the unpaid balance of the Contract
Price, the Owner shall pay the Contractor the difference, and
.4 on expiry of the warranty period, charge the Contractor the amount by which the cost of corrections to the
Contractors work under eye 1 ;L? . WARRAN'r"'{ exceeds the allowance provided for such corrections, or
if the cost of such corrections is less than the allowance, pay the Contractor thc difference.
eeDe 2 -1994 File00712 24
Thi.l' contrad L~ prolecled by CopYrlghl. li,,'c ora ceDe' 2 documenllwt con/oimng a CeDC 2 copyri;.;hl .l'ea! nmslllule,,' an mjringementoFCopynghl Only sigll/his
('on/rad i/'lhe document co\'er pag" hears a CCD(' 2 copyright seal/o demo/l.l"/ra/e Inm il ir in/ended hy Ihe parlies /0 be an accurate and unamended venio/l oICCIX' J
1994 exceptio Ihe exlenllhal any alterations, addiliom or mod!jimlior/.!' are sel forth in supplemenlary (vndition.l'
7.1.6 The Contractor's obligation under the Contract as to quality, correction, and warranty of the work performed
by the Contractor up to the time oftennination shall continue in force after such termination.
GC 7.2 CONTRACTOR'S RIGHT TO STOP THE WORK OR TERMINATE THE CONTRACT
7.2.1 If the Owner should be adjudged bankrupt, or makes a general assignment for the benefit of creditors because
of the Owner's insolvency, or if a receiver is appointed because of the Owners insolvency, the Contractor may,
without prejudice to any other right or remedy the Contractor may have, by giving the {ht,ner or receiver or
trustee in bankruptcy notice in writing, terminate the Contract.
7.2.2 lfthe Work should be stopped or otherwise delayed for a period of30 days or more under an order of a court or
other public authority and providing that such order was not issued as the result of an act or fault of the
Contractor or of anyone directly or indirectly employed or engaged by the Contractor, the Contractor may,
without prejudice to any other right or remedy the Contractor may have, by giving the (h1mer notice in \vriting,
terminate the Contract.
7.2.3 The Contractor may notify the {ht,-ner in ""Titing, with a copy to the Consultant, that the Owner is in default of
the o.vners contractual obligations if:
.1 the Owner fails to furnish, when so requested by the Contractor, reasonable evidence that financial
arrangements have been made to fulfill the Owners obligations under the Contract, or
.2 the Consultant fails to issue a certificate as provided in GC :\3 PHJ)(3RI<SS P.A'{MENT, or
.3 the Owner fails to pay the Contractor when due the amounts certified by the Consultant or awarded by
arbitration or court, or
.4 the (hmer violates the requirements of the Contract to a substantial degree and the Consultant, except for
GC 5.1 FlNi\\(T\C INFORMATION REQCJRED 01 IIIi' OW\i'R, confirms by written statement
to the Contractor that sufticient cause exists.
7.2.4 The Contractor's notice in \'{fiting to the Owner provided under paragraph 7.2.3 shall advise that if the default
is not corrected within 5 Working Days following the receipt of the notice in "vriting, the Contractor may,
without prejudice to any other right or remedy the Contractor may have, stop the Work or terminate the
Contract.
7.2.5 lfthe Contractor terminatcs the Contract under the conditions set out above, the Contractor shall be entitled to
be paid for all work performed including reasonable profit, for loss sustained upon Products and construction
machinery and equipment, and such other damages as the Contractor may have sustained as a result of the
termination ofthe Contract.
PART 8 DISPUTE RESOLUTION
GC 8.1 AUTHORITY OF THE CONSULTANT
8.1.1 Differences betv.reen the parties to the Contract as to the interpretation, application or administration of the
Contract or any failure to agree where agreement between the parties is called for, herein collectively called
disputes, which are not resolved in the first instance by findings of the Consultant as provided in ()C
R()Lr~ OF TH[~ C\JNSLLTAN1, shall bc settled in accordance with the requirements of Part 8 of the General
Conditions - DISPUTE RESOLUTIOX
8.1.2 If a dispute arises under the Contract in respect of a matter in which the Consultant has no authority under the
Contract to make a finding, the procedures set out in paragraph 8.1.3 and paragraphs 8.2.3 to 8.2.8 of
ceDe 2 - 1994 File 00712 25
Thi,y confyocl is protected by Copyright. Use r?fa CeDe 2 document nol comaining 0 CeDe 2 copynghr xeal conxtilutes an infringemem of Copyright. Only sign /his
wntnKt iflhe document co]'er page bears a CCJX~ 2 copyrighl seal 10 demon.llrale thol it i.1 intended by Ihe parlies to be on o",'urale and unammded vcr.,ion o{ccrX' 2
1994 e.;r:cept to the extentth"t any aiterations, additions or modifications ore :;etforlh in supplementary conditions
GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION, and in GC X i RETENTION 01' P1GIlTS
apply to that dispute v-.ith the necessary changes to detail as may be required.
8.1.3 If a dispute is not resolved promptly, the Consultant shall give such instructions as in the Consultant's opinion
are necessary for the proper performance of the Work and to prevent delays pending settlement of the dispute.
The parties shall act immediately according to such instructions, it being understood that by so doing neither
party wi II jeopardize any claim the party may have. If it is subsequently determined that such instructions were
in error or at variance with the Contract Documents, the Olvner shall pay the Contractor costs incurred by the
Contractor in carrying out such instructions which the Contractor was required to do beyond what the
Contract Documents correctly understood and interpreted would have required, including costs resulting from
interruption of the Work.
GC 8.2 NEGOTIATION, MEDIATION, A:'oID ARBITRATION
8.2.1 In accordance with the latest edition of the Rules for Mediation of CCDC 2 Construction Disputes, the parties
shall appoint a Project Mediator
8.2.2
8.2.3
8.2.4
8.2.5
8.2.6
8.2.7
.1 \\rithin 30 days after the Contract was awarded, or
.2 if the parties neglected to make an appointment ,\rithin the 30 day period, within 15 days after either party
by notice in writing requests that the Project Mediator be appointed.
A party shall be conclusively deemed to have accepted a finding of the Consultant under (lC 2,2 ROLE ()F
111[' CO'\SULTANT and to have expressly waived and released the other party from any claims in respect of
the particular matter dealt with in that finding unless, within 15 Working Days after receipt of that finding, the
party sends a notice in writing of dispute to the other party and to the Consultant, which contains the particulars
of the matter in dispute and the relevant provisions of the Contract Documents. The responding party shall
send a notice in writing of reply to the dispute within 10 Working Days after receipt of the notice of dispute
setting out particulars of this response and any relevant provisions of the Contract Documents.
The parties shall make all reasonable efforts to resolve their dispute by amicable negotiations and agree to
provide, without prejudice, frank, candid and timely disclosure of relevant facts, information, and documents to
facilitate these negotiations.
After a period of 10 Working Days following receipt of a responding party's notice in writing of reply under
paragraph 8.2.2, the parties shall request the Project Mediator to assist the parties to reach agreement on any
unresolved dispute. The mediated negotiations shall be conducted in accordance with the latest edition of the
Rules for Mediation ofCCDC 2 Construction Disputes.
If the dispute has not been resolved within 10 Working Days after the Project Mediator was requested under
paragraph 8.2.4 or within such further period agreed by the parties, the Project Mediator shall terminate the
mediated negotiations by giving notice in writing to both parties.
By giving a notice in writing to the other party, not later than 10 Working Days after the date of termination of
the mediated negotiations under paragraph 8.2.5, either party may refer the dispute to be finally resolved by
arbitration under the latest edition of the Rules for Arbitration of CCDC 2 Construction Disputes. The
arbitration shall be conducted in the jurisdiction of the Place q,fthe Work.
On expiration of the 10 Working Days, the arbitration agreement under paragraph 8.2.6 is not binding on the
parties and, if a notice is not given under paragraph 8.2.6 within the required time, the parties may refer the
unresolved dispute to the courts or to any other form of dispute resolution, including arbitration, which they
have agreed to use.
eeDe 2 - 1994 File 00712
26
Thi!" wnrracl i!' prO/erled by Copyright. U.I'e ora CCIX: 2 Joeumen! nor conlainmg a eeDe 2 copyrighl seal ('fIns/illlte,I' an infringemenl orCopynghl, Unly xlgnlhJ.\'
controcl irlhe documenl COI'er page hear.\" a CCIX~ 2 mpyrigl1l seal to demon.l'lrote Il1al il ix intended hy Ihe parliex to he an acclIrale and unamended version orCC"/X 2
/994 e.xcept 10 Ihe atm/ Ihal anyallera/iom, additions or modijicationJ are sel!orth in .\'upplemenwry conditions
8.2.8 If neither party requires by notice in writing given within 10 Working Days of the date of notice requesting
arbitration in paragraph 8.2.6 that a dispute be arbitrated immediately, all disputes referred to arbitration as
provided in paragraph 8.2.6 shall be
.1 held in abeyance until
(1) Substantial Performance of the Work,
(2) the Contract has been terminated, or
(3) the Contractor has abandoned the Work,
whichever is earlier, and
.2 consolidated into a single arbitration under the rules governing the arbitration under paragraph 8.2.6.
GC 8.3 RETENTION OF RIGHTS
8.3.1 It is agreed that no act by either party shall be construed as a renunciation or waiver of any rights or recourses,
provided the party has given the notices required under Part 8 of the General Conditions - DISPUTE
RESOLUTION and has carried out the instructions as provided in paragraph 8.] .3.
8.3.2 Nothing in Part 8 of the General Conditions - DISPUTE RESOLUTION shall be construed in any way to limit
a party from asserting any statutory right to a lien under applicable lien legislation of the jurisdiction of the
Place of the Work and the assertion of such right by initiating judicial proceedings is not to be construed as a
waiver of any right that party may havc under paragraph 8.2.6 to proceed by way of arbitration to adjudicate
the merits of the claim upon which such a lien is based.
PART 9 PROTECTION OF PERSONS AND PROPERTY
GC 9.1 PROTECTION OF WORK AND PROPERTY
9.1.1 The Contractor shall protect the Work and the Owner's property and property adjacent to the Place qfthe Work
from damage which may arise as the result of the Contractor's operations under the Contract, and shall be
responsible for such damage, except damage which occurs as the result of:
.1 errors in the Contract Documents;
.2 acts or omissions by the (Avner, the Consultant, other contractors, their agents and employees.
9.1.2 Should the Contractor in the performance of the Contract damage the Work, the Owners property, or property
adjacent to the Place of the Work, the Contractor shall be responsible for the making good such damage at the
Contractors expense.
9.].3 Should damage occur to the Work or Owner's property for which the Contractor is not responsible, as provided
in paragraph 9.1.1, the Contractor shall make good such damage to the Work and, if the Owner so directs, to
the Owner's property. The Contract Price and Contract Time shall be adjusted as provided in (ie' (,
CIIA~<()E.,5L erC 6.2 -, CJli\'\GE ORDER.. and (iC' 6_3 -- CTL-\'<CiE fllRLC'Tl\-'L.
GC 9.2 DAMAGES AND MUTUAL RESPONSIBILITY
9.2.1 If either party to the Contract should suffer damage in any manner because of any Mongful act or neglect of
the other party or of anyone for whom the other party is responsible in law, then that party shall be reimbursed
by the other party for such damage. The reimbursing party shall be subrogated to the rights of the other party
in respect of such wrongful act or neglect if it be that of a third party.
eeDe 2 - 1994 File 00712
27
Thi.\' cOn/ruC! ix protected by Copyrighl. Use ofa CCIX.' 2 documenl nOI cOnlaininK a CeDe 2 copyr(r;hl seal ('omtiWle:;- an ill/hngemenl afCopyright Only .\'ign Ihis
mntracl If the documenf emu page bears a CCD(' 2 ,'ap;.-ri&4JI.I'eallo Jemo/l,\lrale thD/ it h intended by Ihe parlie~ ta be an accurate and unamended version ofCCrx~ 2-
1994 except to the exten! that any alteration~. additions or mrx}i/imtiom' are Ie/forlh in supplementary collditlom'
9.2.2 Claims for damage under paragraph 9.2.1 shall be made in writing to the party liable within reasonable time
after the first observance of such damage and if undisputed shall be confirmed by Change Order. Disputed
claims shall be resolved as set out in Pari 8 of the (teDera] Condition:'> DfSPIJTE RE:SOLCTION.
9.2.3 If the Contractor has caused damage to the work of another contractor on the Project, the Contractor agrees
upon due notice to settle with the other contractor by negotiation or arbitration. If the other contractor makes a
claim against the Owner on account of damage alleged to have been so sustained, the Owner shall notify the
Contractor and may require the Contractor to defend the action at the Contractors expense. The Contractor
shall satisfY a final order or judgment against the Owner and pay the costs incurred by the (fivner arising from
such action.
9.2.4 If the Contractor becomes liable to payor satisfy a final order, judgment, or award against the Owner, then the
Contractor, upon undertaking to indemnify the Owner against any and all liability for costs, shall have the right
to appeal in the name of the Owner such final order or judgment to any and all courts of competent jurisdiction.
GC 9.3 TOXIC A'\TD HAZARDOUS SUBSTANCES AND MATERIALS
9.3.1 For the purposes of applicable environmental legislation, the Owner shall be deemed to have control and
management of the Place of the Work with respect to existing conditions.
9.3.2 Prior to the Contractor commencing the Work, the Owner shall
.1 take all reasonable steps to determine whether any toxic or hazardous substances or materials are present
at the Place of the Work, and
.2 provide the Consultant and the Contractor with a written list of any such substances and materials.
9.3.3 The Owner shall take all reasonable steps to ensure that no person suffers injury, sickness, or death and that no
property is injured or destroyed as a result of exposure to, or the presence of, toxic or hazardous substances or
materials which were at the Place of the Work prior to the Contractor commencing the Work.
9.3.4 Unless the Contract expressly provides otherwise, the Cht.-ner shall be responsible for taking all necessary
steps, in accordance with legal requirements, to dispose of, store or othenvise render hannless toxic or
hazardous substances or materials which were present at the Place of the Work prior to the Contractor
connnencing the Work.
9.3.5 If the Contractor
.1 encounters toxic or hazardous substances or materials at the Place of the Work, or
.2 has reasonable grounds to believe that toxic or hazardous substances or materials are present at the Place
afthe Work,
which were not disclosed by the Owner, as required under paragraph 9.3.2, or which were disclosed but have
not been dealt with as required under paragraph 9.3.4, the Contractor shall
.3 take all reasonable steps, including stopping the Work, to ensure that no person suffers injury, sickness, or
death and that no property is injured or destroyed as a result of exposure to or the presence of the
substances or materials, and
.4 immediately report the circumstances to the Consultant and the ()v,mer in 'Nfiting.
ceDe 2 - 1994 File 00712
28
This contraclls proteeted by Copyright. Uiie (!!a CClf 2 document nO! con/aininl{ a CCDC 2 copynghl seal comli/ute.I' an infringemem ofCopyrighl. Only iiign Ihis
contraet iflhe do("umefl/ cover page bears a ('('IX' 2 mpJriglll sea/to demonstrate Ihal il i.I' intended hJ {he parlie~' to be an accurWf und unamended version ofCCDC 2-
1994 excepl to the extent thai any alterations, additiom or modijka/ions are setforth in supplementary ("Nidi/ions
9.3.6 If the Contractor is delayed in performing the Work or incurs additional costs as a result of taking steps
required under paragraph 9.3.5.3, the Contract Time shall be extended for such reasonable time as the
Consultant may recommend in consultation with the Contractor and the Contractor shall be reimbursed for
reasonable costs incurred as a result of the delay and as a result of taking those steps.
9.3.7 Notwithstanding pamgIaphs 2.2.6 :md 2.2.7 ofC;C 2.2 -"j{(}LF, C)F IlfE CONSLLT,'\NT, or i;.1
oI (IC 8.1 . AUTHORITY OF n IE CONSULT,\ NT, the Consultant may select and rely upon the advice of
an independent expert in a dispute under paragraph 9.3.6 and, in that case, the expert shall be deemed to have
been jointly retained by the (fimer and the Contractor and shall be jointly paid by them.
9.3.8 The Owner shall indemnify and hold harmless the Contractor, the Consultant, their agents and employees,
from and against claims, demands, losses, costs, damages, actions, suits, or proceedings arising out of or
resulting from exposure to, or the presence of, toxic or hazardous substances or materials which were at the
Place of the Work prior to the Contractor commencing the Work. This obligation shall not be construed to
negate, abridge, or reduce other rights or obligations of indemnity set out in (iC 1:2.1 1\ DEfv!NIFICi\TICi\'
or which otherwise exist respecting a person or party described in this paragraph.
9.3.9 GC 9.3 . TOXIC AND HAZARDOUS SUBSTANCES AND MATERIALS shall govern over the provisions
of U.I 01 G( '.' IUGIITS AND REMEDIES or GC 9.2 . DAMAGES AND MUTUAL
RESPONSffiILITY.
PART 10 GOVERNING REGULATIONS
GC 10.1 TAXES AND DUTIES
10.1.1 The Contract Price shall include all taxes and customs duties in effect at the time of the bid closing except for
Value Added Taxes payable by the Owner to the Contractor as stipulated in Article /\-4 of the Agreement-
CONTRACT PRICE.
10.1.2 Any increase or decrease in costs to the Contractor due to changes in such included taxes and duties after the
time ofthe bid closing shall increase or decrease the Contract Price accordingly.
GC 10.2 LAWS, NOTICES, PERMITS, AND FEES
10.2.1 The laws oftheP/ace of the Work shall govern the Work.
10.2.2 The Owner shall obtain and pay for the building pennit, permanent easements, and rights of servitude. The
Contractor shall be responsible for pennits, licenses, or certificates necessary for the performance of the Work
which were in force at the date of bid closing.
10.2.3 The Contractor shall give the required notices and comply with the laws, ordinances, rules, regulations, or
codes which are or become in force during the performance of the Work and which relate to the Work, to the
preservation of the public health, and to construction safety.
10.2.4 The Contractor shall not be responsible for veritying that the Contract Documents are in compliance with the
applicable laws, ordinances, rules, regulations, or codes relating to the Work. If the Contract Documents are at
variance therewith, or if, subsequent to the date of bid closing, changes are made to the applicable laws,
ordinances, rules, regulations, or codes which require modification to the Contract Document."" the Contractor
shall notify the Consultant in writing requesting direction immediately upon such variance or change becoming
known. The Consultant will make the changes required to the Contract Documents as provided in (iC 6.1
CIIANCiES, GC 6.2 ClL\:\Gi. ORDER, and (Ie 6.3 CII:\NUli DIRECTlVF.
CCDe 2.1994 File 00712
29
This ('antracl is pro/ecled by Copyrigh/. [.i,I'e of a eelX-' 2 document nOI contaimng a CCDC 2 copyrighl ,wml com-/illl/e,I' an mfringemen/ ofCopynghl. Only ,,'Ign this
con/racl ifilJe documenl cover page hears a ccrx~ 2 copyrighl seal/o demons/role zhm il ix in/ended hy Ihe porlie.,' /0 he an <<ccum/" and unamended l'erIion ojCCTX' 2
1994 excep//o the extent/hat any ahera/ions, uddi/ion:i or modljications are xetfiJrlh in supplementary condilions.
10.2.5 If the Contractor fails to notify the Consultant in writing; and fails to obtain direction as required in paragraph
10.2.4; and performs work knowing it to be contrary to any laws, ordinances, rules, regulations, or codes; the
Contractor shall be responsible for and shall correct the violations thereof; and shall bear the costs, expenses,
and damages attributable to the failure to comply with the provisions of such laws, ordinances, rules,
regulations, or codes.
GC 10.3 PATENT FEES
10.3.1 The Contractor shall pay the royalties and patent licence fees required for the performance of the Contract.
The Contractor shall hold the Ovvner harmless from and against claims, demands, losses, costs, damages,
actions, suits, or proceedings arising out of the Contractor's performance of the Contract which are attributable
to an infringement or an alleged infringement of a patent of invention by the Contractor or anyone for whose
acts the Contractor may be liable.
10.3.2 The Owner shall hold the Contractor harmless against claims, demands, losses, costs, damages, actions, suits,
or proceedings arising out of the Contractor's performance of the Contract which are attributable to an
infringement or an alleged infringement of a patent of invention in executing anything for the purpose of the
Contract, the model, plan, or design of which was supplied to the Contractor as part of the Contract
Documents.
GC lOA WORKERS' COMPENSATION
10.4.1 Prior to connnencing the Work, Substantial Performance of the Work, and the issuance of the final certificate
for payment, the Contractor shall provide evidence of compliance '.Vith workers' compensation legislation at
the Place of the Work, including payments due thereunder.
10.4.2 At any time during the term of the Contract, when requested by the OlJ,.'ner, the Contractor shall provide such
evidence of compliance by the Contractor and Subcontractors.
PART 11 INSURANCE-BONDS
GC 11.1 I:'oISURANCE
11.1.1 Without restricting the generality oftle' [2. [ lNDF;:rvfNTFfC:ATION, the Contractor shall provide, maintain,
and pay for the insurance coverages specified in OC 11.1 - INSURANCE. Unless otherwise stipulated, the
duration of each insurance policy shall be from the datc of commencement of the Work until the date of the
final certificate for payment. Prior to connnencement of the Work and upon the placement, renewal,
amendment, or extension of all or any part of the insurance, the Contractor shall promptly provide the Owner
with confirmation of coverage and, if required, a certified true copy of the policies certified by an authorized
representative of the insurer together with copies of any amending endorsements.
.1 General Liability Insurance:
General liability insurance shall be in the joint names of the Contractor, the Owner, and the Consultant,
'.Vith limits of not less than $2,000,000 per occurrence and with a property damage deductible not
exceeding $2,500. The insurance coverage shall not be less than the insurance required by IBC Form
2100, or its equivalent replacement, provided that IBC Form 2100 shall contain the latest edition of the
relevant CeDe endorsement form. To achieve the desired limit, wnbrella, or excess liability insurance
may be used. AU liability coverage shall be maintained for completed operations hazards from the date of
Substantial Petjormance of the Work, as set out in the certificate of Substantial Performance of the Work,
on an ongoing basis for a period of 6 years following Substantial Performance of the Work. Where the
Contractor maintains a single, blanket policy, the addition of the Ol1,-ner and the Consultant is limited to
liability arising out of the Project and all operations necessary or incidental thereto. The policy shall be
eeDe 2.1994 File 00712 30
This contracl il' proteeled by Copyright. Ule o/Q ('('IX: 2 documenl nol containing a CCIX' 2 copyright .\"1'01 COnI/itute.I' Qn infringement 01 Copyright. Only.liWI/hi.l'
cuntract [('(he documen! COl'er page h<:ars a CeDe 2 copyright .I'ealto demomlrate rha{ II is intended by {he panic.1 10 h<: an accurate and unamended WH.I'lOn 'iICCU' 2
1994 e:.n::epl/o the exlentlhat any alteratiollS. addiliom or !1Iodilicwiolls are sdjorlh ill supplementary conditions.
endorsed to provide the Owner with not less than 30 days notice in writing in advance of any cancellation,
and of change or amendment restricting coverage.
.2 Automobile Liability Insurance:
Automobile liability insurance in respect of licensed vehicles shall have limits of not less than $2,000,000
inclusive per occurrence for bodily injury, death, and damage to property, covering all licensed vehicles
owned or leased by the Contractor, and endorsed to provide the Owner with not less than 15 days notice
in 'Nriting in advance of any cancellation, change or amendment restricting coverage. Where the policy
has been issued pursuant to a government-operated automobile insurance system, the Contractor shall
provide the Owner with confirmation of automobile insurance coverage for all automobiles registered in
the name of the Contractor.
.3 Aircraft and Watercraft Liability Insurance:
Aircraft and watercraft liability insurance with respect to owned or non-owned aircraft and watercraft if
used directly or indirectly in the performance of the fVork, including use of additional premises, shall be
subject to limits of not less than $2,000,000 inclusive per occurrence for bodily injury, death, and damage
to property including loss of use thereof and limits of not less than $2,000,000 for aircraft passenger
hazard. Such insurance shall be in a form acceptable to the O'v'mer. The policies shall be endorsed to
provide the Owner with not less than 15 days notice in 'Nriting in advance of cancellation, change, or
amendment restricting coverage.
.4 Property and Boiler and Machinel1" Insurance:
(1) "All risks" property insurance shall be in the joint names of the Contractor, the Owner, and the
Consultant, insuring not less than the sum of the amount of the Contract Price and the full value, as
stated in the Supplementary Conditions, of Products that are specified to be provided by the (ll-vner
for incorporation into the Work, with a deductible not exceeding $2,500. The insurance coverage
shall not be less than the insurance required by IBC Form 4042 or its equivalent replacement,
provided that IBC Form 4042 shall contain the latest edition of the relevant CCDC endorsement form.
The coverage shall be maintained continuously until 10 days after the date of the final certificate for
payment.
(2) Boiler and machinery insurance shall be in the joint names of the Contractor, the Owner, and the
Consultant for not less than the replacement value of the boilers, pressurc vessels, and other insurable
objects forming part of the Work. The insurance provided shall not be less than the insurance
provided by the "Comprehensive Boiler and Machinery Form" and shall be maintained continuously
from commencement of use or operation of the property insured and until 10 days after the datc of the
final certificate for payment.
(3) The policies shall allow for partial or total use or occupancy of the Work. Ifbecause of such use or
occupancy the Contractor is unable to provide coverage, the Contractor shall notify the Ovvner in
\vriting. Prior to such use or occupancy the Owner shall provide, maintain, and pay for property and
boiler insurance insuring the full value of the fVork, as in sub-paragraphs (1) and (2), including
coverage for such use or occupancy and shall provide the Contractor with proof of such insurance.
The Contractor shall refund to the Owner the unearned premiums applicable to the Contractor's
policies upon tennination of coverage.
(4) The policies shall provide that, in the case ofa loss or damage, payment shall be made to the Owner
and the Contractor as their respective interests may appear. The Contractor shall act on behalf of the
Owner for the purpose of adjusting the amount of such loss or damage payment with the insurers.
When the extent of the loss or damage is determined, the Contractor shall proceed to restore the
Work. Loss or damage shall not affect the rights and obligations of either party under the Contract
except that the Contractor shall be entitled to such reasonable extension of Contract Time relative to
eeDe 2 - 1994 File 00712
31
Thi.\' con/rod is pro/eeled by Copyright. Use (!lu CCDe 2 document no/ containing a eeDe 2 copYflghr seal cunsli/u/es an infringement ofCopyrigh/. Only sign Ihis
con/racl ijrhe document ('(J)'ef page bears a CCDe 2 mpyrighlseal/IJ demons/ra/e lhar il is in/ended by rhe parlie.I' /0 he an aCC71rale and unamended version n(CCDC 2--
1994 exceptio the exlent/hat all)" ullerat;orlS, additions or modifications are se/forth in supplemen/ary conditions.
the extent of the loss or damage as the Consultant may recommend in consultation with the
Contractor.
(5) The Contractor shall be entitled to receive from the Owner, in addition to the amount due under the
Contract, the amount at which the Owner's interest in restoration of the Work has been appraised,
such amount to be paid as the restoration of the Work proceeds and as provided in (;(~ 52
,-\Pl'UC;\'T10\S FOn. Pj{{)(iRL.:8S PAY\-lLNT' and CC 5.3 ~ PT{()(jRESS Pi\, \'Mf;'NT. In
addition the Contractor shall be entitled to receive from the payments made by the insurer the amount
of the Contractor's interest in the restoration of the Work.
(6) In the case of loss or damage to the Work arising from the work of another contractor, or Owner's own
forces, the Owner, in accordance with the Owner's obligations under 32,2>-1 of GC 3,2
CONSTRUCTION BY OWNCR OR OTIIER CONTHACIORS, shall pay the Contractor the cost
of restoring the Work as the restoration of the Work proceeds and as provided in (!e
APFLJC/\TfONS FUR PRC)fjRESS PA Yl\iIL<\'] and G(' 5,3 PFOGKL':SS Pi\ '{\/lL>rr.
.5 Contractors' Equipment Insurance:
"All risks" contractors' equipment insurance covering construction machinery and equipment used by thc
Contractor for the performance of the Work, including boiler insurance on temporary boilers and pressure
vessels, shall be in a form acceptable to the Chvner and shall not allow subrogation claims by the insurer
against the Owner. The policies shall be endorsed to provide the Owner with not less than 15 days notice
in writing in advance of cancellation, change, or amendment restricting coverage. Subject to satisfactory
proof of financial capability by the Contractor for self-insurance, the (ll-vner agrees to waive the
equipment insurance requirement.
11.1.2 The Contractor shall be responsible for deductible amounts under the policies except where such amounts may
be excluded from the Contractor's responsibility by the terms of C;(' (lI - PRCirl,Cff(}N (H' \\/ORK AND
PROPL:RTY and (r(:' (j.2 ..J.j,\t\:lA(jL,:S"1.ND \:lU'CUAL RLSP()l\SiEJLJTY.
11.1.3 \\'here the full insurable value of the Work is substantially less than the Contract Price, the Owner may reduce
the amount of insurance required or waive the course of construction insurance requirement.
11.1.4 If the Contractor fails to provide or maintain insurance as required by the Contract Documents, then the
(hmer shall have the right to provide and maintain such insurance and give evidence to the Contractor and the
Consultant. The Contractor shall pay the cost thereof to the Ovvner on demand or the Owner may deduct the
amount which is due or may become due to the Contractor.
11.1.5 All required insurance policies shaH be with insurers licensed to underwrite insurance in the jurisdiction of the
Place of the Work.
GC 11.2 BONDS
11.2.1 The Contractor shall, prior to commencement of the Work or within the specified time, provide to the Ort.ner
any surety bonds required by the Contract.
11.2.2 Such bonds shall be issued by a duly licensed surety company authorized to transact a business of suretyship in
the province or territory of the Place o/the Work and shall be maintained in good standing until the fulfilment
of the Contract. The form of such bonds shall be in accordance with the latest edition of the CeDe approved
bond forms.
CCDC2-1994Fi1e00712
32
Thi.~ contract i.I' protecled by Copyright. [III' (!fa CCOC 2 docl/menj not comaining a CCDC 2 copYrlghl xeol ,'onslituleI an in,tringemen! ofC'opyrighl. Onl)! ,l'ign Ihis
wnlracllfihe doel/men! cowr pafiC bears a CCDe 2 copyrif:ht sea/to demonsrrate Ihat it is intended by the parries to he on oceurale alld unamended l'enion o{Ccrx 2
1994 except 10 the extent thai any aiterotio/l.l, addition.\" or fflodificaliof/s are .Ie/forth in supplementary wnditio/ls
PART 12 INDEMNIFICATION - WAIVER- WARRANTY
GC 12.1 INDEMNIFICATION
12.l.1 The Contractor shall indemnifY and hold harmless the Owner and the Consultant, their agents and employees
from and against claims, demands, losses, costs, damages, actions, suits, or proceedings (hereinafter called
"claims"), by third parties that arise out of, or are attributable to, the Contractor's perfonnance of the Contract
provided such claims are:
.1 attributable to bodily injury, sickness, disease, or death, or to injul)' to or destruction of tangible property,
and
.2 caused by negligent acts or omissions of the Contractor or anyone for \",'hose acts the Contractor may be
liable. and
.3 made in \"'Titing within a period of6 years from the date of Substantial Performance of the f,Vork as set out
in the certificate of Substantial Performance of the JYork, or within such shorter period as may be
prescribed by any limitation statute of the province or territoI)' of the Place qf the Work.
The Owner expressly viaives the right to indemnity for claims other than those stated above.
12.1.2 The obligation of the Contractor to indemnifY hereunder shall be limited to $2,000,000 per occurrence from
the conunencement of the Work until Substantial Performance of the Work and thereafter to an aggregate limit
of $2,000,000.
12.1.3 The Owner shall indemnifY and hold harmless the Contractor, the Contractors agents and employees from and
against claims, demands, losses, costs, damages, actions, suits, or proceedings arising out of the Contractor's
performance of the Contract v,:hich are attributable to a lack of or defect in title or an alleged lack of or defect
in title to the Place of the Work.
12.1.4 GC 12.1 -INDEMNIFICATION shall govern over the provisions of 13.lof(;( .3 - I<I(;IITS
/\\i)RL,\'lEDILS or CC: 9.2 ~l)A\'l:\(;ES AND \l(_i-il;'ALRL:.~l)()NS!nlLr[-\",
GC 12.2 WAIVER OF CLAIMS
12.2.1 Waiver of Claims by OUlner
As of the date of the final certificate for payment, the Olvner expressly waives and releases the Contractor
from all daims against the Contractor including v,:ithout limitation those that might arise from the negligence
or breach of contract by the Contractor except one or more of the lo11oviing:
.1 those made in VvTiting prior to the date of the final certificate for payment and still unsettled;
.2 those arising from the provisions ofGC 12.1 -INDEMNIFICATION or GC 12.3 - WARRANTY;
.3 those arising tram the provisions of 9__'5 i)l' fie 9,3 - TC)XH '\'\1) JL\!.\RDO\ "-
SUHST.\NCES /\ND M/\llJZL-\I..S and arising from the Contractor bringing or introducing any toxic or
hazardous substances and materials to the Place of the ~Vork after the Contractor commences the Work.
In the Common Law provinces GC 12.2.1.4 shall read as follows:
.4 those made in \'vTiting vvithin a period of6 years from the date of Substantial Performance of the Work, as
set out in the certificate of Substantial Pe'formance of the Work, or within such shorter period as may be
eeDe 2 - 1994 File 00712
33R
This contract i,I' protected by Copyright. U.I'e ofa CCLl(' 2 Jocumen/ not containing a CC[X~ 2 cOPYr/gh/ .I'wl cons/itutes an i~fringement ofCopyr/ghl, Only sign this
con/rocl if'lIw w)Cument corer page bear.1 a CCIX:' 2 copyright .\'eal/o demons/role thai it i,I' in/ended by Ihe par/ie,,' /0 be an an:urate and unamended venlun rgCCTX' 2
1994 ecepllO /ne exten/tnal any ai/era/lam, addition.>' or modi/ications un; .w:!lforth in ,l'Upplememary conditions
prescribed by any limitation statute of the province or territory of the Place of the Work and arising from
any liability of the Contractor for damages resulting from the Contractor's performance of the Contract
with respect to substantial defects or deficiencies in the Work for which the Contractor is proven
responsible.
As used herein "substantial defects or deficiencies" means those defects or deficiencies in the ff"ork \\lhich
atlect the Work to such an extent or in such a manner that a significant part or the whole of the Work is unfit for
the purpose intended by the Contract Documents.
In the Province of Quebec GC 12.2.1.4 shall read as foHo\\ls:
.4 those arising under the provisions of Article 2118 of the Civil Code of Quebec.
12.2.2 Waiver of Claims by Contractor
As of the date of the final certificate for payment, the Contractor expressly waives and releases the (MIner
from all claims against the Owner including without limitation those that might arise from the negligence or
breach of contract by the Chj!ner except:
.1 those made in wTiting prior to the Contractor's application for final payment and still unsettled; and
.2 those arising from the provisions of (;C' 93 - f\l\lC' ANL) f-L:\ZARDOliS SUBSTANCES ;,\ND
\lf~'l'F',RT/\l,S or GC ]n.3 - PArl:""-!' 1;[1:8<
12.2.3 GC 12.2 - WAIVER OF CLAIMS shall govern over the provisions of paragraph 1 ;,1 or (Je' .3" H,JCiHTS
'\,\0 REMEDIES or OC 9,1-UA\-li\GH c\\1l MUll Al RI'SFONSU3IU I Y,
GC 12.3 WARRANTY
12.3.1 The warranty period with regard to the Contract is one year from the date of Substantial Performance of the
f1/ork or those periods specified in the Contract Documents for certain portions of the f-.Vork or Products.
12.3.2 The Contractor shall be responsible for the proper performance of the Work to the extent that the design and
Contract Documents permit such performance.
12.3.3 Except for the provisions of paragraph 12.3.6 and subject to paragraph 12.3.2, the Contractor shall correct
promptly~ at the Contractor's expense, defects or deficiencies in the Work which appear prior to and during the
warranty periods specified in the Contract Documents.
12.3.4 The Owner) through the Consultant, shall promptly give the Contractor notice in writing of observed defects
and deficiencies that occur during the warranty period.
12.3.5 The Contractor shall correct or pay for damage resulting from corrections made under the requirements of
paragraph 12.3.3.
12.3.6 The Contractor shall be responsible for obtaining Product warranties in excess of one year on behalf of the
Owner from the manufacturer. These Product warranties shall be issued by the manufacturer to the benefit of
the Oi-vner.
eeDe 2 -1994 File 00712
34R
this contract ~\' prOla'led by Copynghl. Ure ufo ccrx: 2 doeuml!nl nol comaining a C(,'D(~ 2 copyright xea! com/itules an injringemr::nI oICup)mghl. Un~y sign Ihi.\'
con/rae! ijlhr doclIme11l cover page bears (1 CClX' 2 copyflghl seal/o demonxlrOle Ihm il i_I" in/ended by Ihe parlJe,\' If) he an a('(urale and unamended version o{'(\~lX' 2-
199./ ecepllO Ihe exlenllhal anyalIera/ions, addi/ionx 01' mod(ficallon.\ are selfurlh in .wpplemenlary conditions
SECTION 00812
SUPPLEMENTARY CONDITIONS
THE GENERAL CONDITIONS OF THE STIPULATED PRICE CONTRACT, STANDARD
CONSTRUCTION DOCUMENT - CCDC 2 - 1994, File 00502, shall be considered
complete only as amended and supplemented by the following
SUPPLEMENTARY CONDITIONS.
1.01
DEFINITIONS
.1
Add new Paragraph:
21. Specifications and Drawings
Specifications and documents included in the Contract
Documents are referred to in the specifications as
Specifications and Drawings.
1.02
GC 3.9
LABOUR AND PRODUCTS
3.9.4
Add new Paragraph:
.1
Perform work under applicable Provincial Codes
and/or labour agreements on a single shift,
straight-time basis for normal hours per week as
defined by the Provincial Codes and/or labour
agreements in force. The cost for overtime
required beyond the normal working day to
complete individual construction operations of a
continuous nature, such as pouring or finishing
of concrete or similar work, or work that the
Contractor elects to perform at overtime rates
without the Owner requesting it, shall not be
chargeable to the Owner.
1.03
GC 3.12
USE OF THE WORK
3.12.3
Add new Paragraphs:
. 1
3.12.4
Project CL2006-12
06.05.24
If work or storage areas in addition to areas
provided by the premises are required, the
Contractor shall be responsible for making
arrangements to obtain the additional areas,
whether adjacent to the premises or not, and for
making permit and rental payments that may be
required.
As used in Paragraph 3.12.3, the 'premises' means
the work site area as enclosed by work site lines
and/or property lines and access thereto as shown
on Drawings, or as designated by the Consultant.
Page 1
1.04
1.05
1.06
1.07
1.08
Section 00812
Supplementary Conditions
GC 5.3
PROGRESS PAYMENT
.1
Amend the phrase "5 days" in Paragraph 5.3.2 to read "30
days" .
GC 5.7
FINAL PAYMENT
.1
Amend the phrase "5 days" in Paragraph 5.7.4 to read "30
days" .
GC 5.5
PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE WORK
Delete GC 5.5.3 in its entirety.
GC 5.6
PROGRESSIVE RELEASE OF HOLDBACK
.1
Add new Paragraph:
5.6.3
Each application for release of Subcontractor's
holdback on totally performed Subcontracts prior
to Substantial Performance of the Work as
permitted under the Construction Lien Act, 1983,
and current amendments, shall be accompanied by
Workers' Compensation Board clearance and a
statutory declaration from the Subcontractor that
the work has been totally performed. The
Statutory Declaration from the subcontractor
shall also contain a statement that all accounts
for labour, subcontractor, products, supplies and
construction machinery, and equipment, which have
been incurred by the Subcontractor, have been
paid in full.
GC 8.2
NEGOTIATION, MEDIATION AND ARBITRATION
8.2.9
Add new Paragraph:
.1
Project CL2006-12
06.05.24
Within 5 days of receipt of the Notice of
Arbitration by the responding party, as
contemplated by Paragraph 8.2.6, the Owner and
the Contractor shall deliver to the Consultant
the following:
a)
b)
Copy of the Notice of Arbitration:
Copy of the Supplementary Conditions 8.2.9 to
Page 2
8.2.10
8.2.11
8.2.12
8.2.13
Project CL2006-12
06.05.24
Section 00812
Supplementary Conditions
c)
8.2.15 or this contract; and
Copies of all written claims, correspondence or
other materials relating to the issues in
dispute, which the Contractor or the Owner, have
forwarded to delivered to each other.
The Owner and the Contractor agree that the
Consultant may elect, within ten days of receipt
of the notice under paragraph 8.2.9 to become a
full party to the arbitration under paragraph
8.2.6 if the Consultant;
a)
has a vested or contingent financial interest in
the outcome of the arbitration;
gives the notice of election to the Owner and the
Contractor before the arbitrator is appointed;
agrees to be a party to the arbitration within
the means of the rules referred to in paragraph
8.2.6; and,
agrees to be bound by the arbitral award made in
the arbitration.
b)
c)
d)
If the Consultant is not given the written notice
required under paragraph 8.2.9, both the Owner
and the Contractor are estopped from pursuing an
action, counter claim or other proceeding or
making an application against the Consultant
arising out of the issues in dispute in the
arbitration between the Owner and the Contractor
under paragraph 8.2.6.
If an election is made under paragraph 8.2.10,
the Consultant may participate in the appointment
of the arbitrator and, notwithstanding the rules
referred to in paragraph 8.2.6, the time period
for reaching agreement on the appointment of the
arbitrator shall begin to run from the date the
respondent receives a copy of the notice of
arbitration.
The arbitrator in the arbitration in which the
Consultant has elected under paragraph 8.2.10 to
become a full party may:
a)
on application of the Owner or the Contractor,
determine whether the Consultant has satisfied
the requirements of paragraph 8.2.10, and;
make any procedural order considered necessary to
facilitate the addition of the Consultant as a
party to the arbitration.
b)
Page 3
8.2.14
8.2.15
1.09
GC 11. 1
INSURANCE
Section 00812
Supplementary Conditions
The provisions of paragraph 8.2.9 shall apply
mutatis mutandis to written notice to be given by
the Consultant to any sub-consultant.
In the event of notice of arbitration given by a
consultant to a sub-consultant, the sub-
consultant is not entitled to any election with
respect to the proceeding as outlined in 8.2.10,
and shall be deemed to be bound by the
arbitration proceeding.
.1
Delete the contents Item GC 11.1 Insurance in its entirety
and replace the contents with the following paragraph:
11.1.1
Proj ect CL2006-12
06.05.24
Without restricting the generality of GC 12.1
IDEMNIFICATION, the Contractor shall provide,
maintain, and pay for the insurance coverages
specified by Tender CL2006-12, forming a part of
this contract.
*
*
*
END OF SECTION
Page 4