HomeMy WebLinkAboutEGD-006-14 Clarington REPORT
ENGINEERING DEPARTMENT
Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE
Date: January 20, 2014 Resolution#: -0(13-1(11 By-law#:
Report#: EGD-006-14 File#:
Subject: OLD SCUGOG ROAD CULVERT REPLACEMENT, BOWMANVILLE,
CONTRACT NO. CL2013-09
RECOMMENDATIONS:
It is respectfully recommended that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report EGD-006-14 be received;
2. THAT capital project over-expenditures in the amount of$46,269.18 be approved
for the Old Scugog Road Culvert Replacement Contract No. CL2013-09;
3. THAT remaining funds from the 2013 Structure Rehabilitation Budget be used to
offset over-expenditures for Old Scugog Road Culvert Replacement Contract No.
CL2013-09;
4. THAT the Department of Engineering Services pursue compensation from Bell
Canada for extra costs relating to their oversight in reporting the location of all
Bell services within the project Ii its.
° } c
Submitted by: Reviewed by: -
A.S. Cannella, C. .T. Franklin Wu,
Director of Engineering Chief Administrative Officer
Services
ASC/RA/dv/jb
January 14, 2014
CORPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L1C 3A6 T 905-623-3379
REPORT NO.: EGD-006-14 PAGE 2
1. PURPOSE
1.1. The purpose of this report is to recommend approval of expenditures in excess of
the additional expenditure limit provided in Administrative and Corporate Policy
H17—Capital Project Over-expenditures—that were incurred on Old Scugog Road
Culvert Replacement, Contract No. CL2013-09.
2. BACKGROUND
2.1. Construction of the Old Scugog Road Culvert Replacement was completed by
Norenco Contracting Ltd. on Sept. 19, 2013. The site is approximately 200 m
south of Concession Rd 9. The total estimated project cost approved by Council
during the award of the tender was $226,000.00 (see Attachment 1 for details).
During construction, the project ran into a number of issues, which are described
in detail below, and total project costs are now estimated to be $272,269.18. This
has created an over expenditure of$46,269.18 that is over the $25,000
contingency allowance limit for projects within the $250,000 cost range authorized
in Policy H17 that can be approved by department directors.
2.2. Extensive negotiations with the contractor regarding Extra Work Orders were
undertaken to lessen the financial impact on the Municipality of Clarington. At this
date, final payment has not yet been forwarded to the contractor, pending Council
approval of the additional funding required to cover these extra costs.
2.3. Despite the unexpected work required to complete the project, staff were able to
work with the Contractor to ensure that the construction was completed on
schedule which was critical due to the working restrictions in the vicinity of a
watercourse. In-water works were completed prior to the Department of Fisheries
and Oceans (DFO) September 15th end-date for in-water works. Adherence to the
in-water works timing window was critical to avoid charges under the Fisheries Act.
2.4. The details of the $46,269.18 in extra charges are provided as follows:
Bell cable excavation and relocation: Two Bell cables were found during the
excavation for the culvert which were not identified by Bell prior to construction.
Extra work involved hand digging to expose the cables, excavation along the
length of the cables to achieve enough slack to relocate the cables around the new
culvert and using a vacuum truck to safely excavate post holes so that the
unidentified Bell cables were not damaged.
Construction and removal of temporary bike path: The Engineering Services
Department was contacted by the United Way to request that cyclists be allowed
to pass through the construction site as part of their Ride 4 United Way event due
to the significant detour that would be required if they could not use Old Scugog
Road. In order to assist with this event, that has considerable benefits for the local
community, Clarington agreed to construct a gravel bike path around the
REPORT NO.: EGD-006-14 PAGE 3
construction site in order for the event users to pass through the site safely and,
following the event, the path was removed and the affected grounds restored.
Removal of second laver of asphalt: The tender called for removal of 50 mm of
surface asphalt. Additional asphalt was discovered at a depth of approximately
200 mm below the surface during excavation which had to be removed and
disposed of as part of the work.
Structure over-dig and backfill due to old timber cribbing and poor subgrade:
During excavation for the culvert, old timber cribs and unsuitable clay subgrade
were encountered which needed to be removed, resulting in a larger than
anticipated excavation. The timber cribs were likely part of an old bridge structure.
The excavation also had to go deeper than anticipated to remove clay subgrade
material in order to have a stable base for the new culvert and gabion retaining
walls. This poor material was outside of the location of our soils investigation and
therefore not able to be identified during the design phase.
3. DISCUSSION
3.1. Extra Work Orders Related to Bell Oversight
Two Bell cables were found during the excavation for the culvert which were not
identified by Bell prior to construction. During the design stage, existing conditions
drawings are sent to the utility companies for them to mark-up any buried plant
that was not visible during the survey. Bell did not identify the location of the
cables, because they did not have them in their own records. Because there was
no record of the cables, they were also not identified on site through the `One Call'
locates process which is done before the Contractor starts excavation.
Bell was not able to mobilize their crews to the site quickly to relocate the cables,
so in order to have the work completed within the allowable working window for the
watercourse; the Municipality's Contractor had to do their best to work around
them. Unfortunately this resulted in them incurring extra costs, which are passed
on to the Municipality.
The Engineering Services Department will be pursuing collection from Bell for a
share of the extra costs associated with the Bell cables. Had the cables been
identified by Bell during the design stage, the Municipality would have required that
Bell re-locate them prior to construction and the Municipality would have been
responsible for a share of the cost; this would have been included in the total
project cost reported to Council. The Municipal Access agreement with Bell
outlines the cost sharing arrangement for relocation work between the Municipality
and Bell. Cost recovery from Bell will reduce the extra costs to be incurred by the
Municipality; this has not been included in the costs described in this report as the
funds have not yet been secured. It is estimated that the charges to be recovered
from Bell would be in the order of roughly $10,000.
REPORT NO.: EGD-006-14 PAGE 4
3.2. Temporary Bike Path
Members of the Bike Friendly group who were involved in the Ride 4 United Way
event were notified in a meeting in early July that Old Scugog Rd would be closed
for the culvert replacement. Based on the contractor's construction schedule, there
was a chance that the road would not be open by the date of the event on Aug. 25.
Due to some of the other problems encountered on this project, there were delays
in construction. Clarington staff was contacted on Aug 19 by United Way to ask if it
would be possible to allow the cyclists to pass through the construction site. A
detour would have required maps to be re-printed and would have resulted in a
considerably longer route. It was agreed that the participants would be permitted to
walk their bikes through the site using a temporary gravel path.
3.3. Remaining Extra Work Orders
A geotechnical investigation was undertaken during the design of the culvert
replacement, and it was determined from the boreholes and analysis that the soil
had adequate bearing capacity to support the culvert. There is always a risk that
there are unforeseen subsurface conditions. While we try to account for the
underground conditions it is not practical or possible to identify all subsurface
issues prior to construction. It is not unusual for there to be extra costs associated
with underground work; however, there were a number of issues at this site which,
in combination, were more expensive than most projects.
4. CONCURRENCE
This report has been reviewed by Nancy Taylor, Director of Finance/Treasurer,
who concurs with the recommendations.
5. CONCLUSION
5.1. Several other structure rehabilitation contracts were issued under the 2013
Structures Rehabilitation budget, all of which were completed under budget, with
one project being deferred to 2014. It is recommended that remaining funds from
the 2013 Structures Rehabilitation budget be used to fund the $46,269.18 over-
expenditure incurred on the Old Scugog Road Culvert Replacement project.
5.2. Engineering Services will continue to pursue cost recovery with Bell for the extra
costs of working around the Bell cables which were not identified by them within
the project limits.
REPORT NO.: EGD-006-14 PAGE 5
CONFORMITY WITH STRATEGIC PLAN — Not Applicable
Staff Contact: Ron Albright, Manager, Infrastructure and Capital Works
Attachments: None
List of interested parties to be advised of Council's decision: Not Applicable