Loading...
HomeMy WebLinkAboutEGD-14-05 C!NilJgron REPORT ENGINEERING SERVICES Meeting: GENERAL PURPOSE AND ADMINISTRATION COMMITTEE Date: Monday April 25, 2005 Report #: EGD-14-05 File#: ?<-e5#; (VJ4-/CI!-DS By-law #: Subject: PORT OF NEWCASTLE CONCEPTUAL WATERFRONT PLAN RECOMMENDATIONS: It is respectfully recommended that the General Purpose and Administration Committee recommend to Council the following: 1. THAT Report EGD-14-05 be received; 2. THAT Phase One of the Conceptual Waterfront Plan for the Port of Newcastle be approved as a guide for the development of a linear waterfront park; 3. THAT staff be authorized to negotiate with Kaitlin for additional waterfront land at the mouth of the Graham Creek and to re-grade the bluff along Lake Ontario; and 4. THAT the proposed erosion control works be referred to the Capital Budget and Forecast. ~ Submitted by: A.S. Cannella, C.E.T. Reviewed by: Franklin Wu, Director of Engineering Services Chief Administrative Officer ASC/PW/jo April 20, 2005 CORPORATION OF THE MUNICIPALITY OF CLARINGTON 40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L lC 3A6 T 905-623-3379 F 905-623-9282 REPORT NO.: EGD-14-05 PAGE 2 1.0 BACKGROUND Through development of the Port of Newcastle subdivision, the Municipality will acquire a 900m long continuous block of District parkland along the Lake Ontario shoreline between Toronto Street and the west edge of the Region of Durham Water Treatment Plant. Additionally the Municipality was granted a 300m long, 15m wide easement from the Kaitlin Group along the waters edge from the east side of the Region's Plant to the pier at the Graham Creek (Attachment 1). The land is intended to be developed as a linear waterfront park with connections to the Samuel Wilmot Nature Area to the west and Graham Creek to the east. Most of the land sits atop a steep bluff 9m to 13m above the level of Lake Ontario. In 2000 The Kaitlin Group, the developers of the subdivision, engaged Marshall Macklin Monaghan Ltd. to work with the Municipality and prepare a conceptual waterfront plan for all of the lands described above. A series of public meetings were held to obtain resident input and a peer review by an independent consultant was used to finalize the conceptual plan. The plan was prepared to provide a conceptual guide for the future development of the parkland and to submit for a second round of SuperBuild funding which did not occur. A key recommendation of the plan is to improve site safety by re-grading the bluff to a 2:1 slope. Kaitlin is currently preparing to develop the western portion of their Port of Newcastle subdivision. As part of that development they can accommodate the fill material generated by re-grading the bluff. They have offered to do the work at their own cost and move the fill material to their next phase of residential development in 2005. If the bluff grading is not done in 2005 then the Municipality would have to re-grade the bluff and truck the fill away from the site in the future. 2.0 CONCEPTUAL WATERFRONT PLAN The location and elevation of the parkland provides a number of opportunities and some significant constraints to development of a District Park. People will be drawn to the area REPORT NO.: EGD-14-05 PAGE 3 for the views out over the lake and proximity to the waters edge. The parkland is also directly adjacent to the Samuel Wilmot Nature Area and is ideally suited for the development of a passive linear park with some active nodes and parking lots on wider portions of the site. The prominent feature of the conceptual waterfront plan will be the development of a 3m wide trail that would meander along the parkland overlooking the lake. The trail would connect to the Samuel Wilmot Nature Area at the west end of the site. At the east end the trail would swing north at the Region's Water Treatment Plant and follow local roads to connect with the existing trail along the Graham Creek at the rear of Carveth Crescent. Due to the potential difficulties and high cost of creating a pedestrian link across the Graham Creek it is proposed that the Waterfront Trail continue north along Port of Newcastle Drive and then south on Mill Street to connect to Bond Head and eventually Lakeshore Road. 2.1 PHASE ONE PARK DEVELOPMENT (Attachment 2) The 7.35 ha (18 acre) park from the Region's Water Treatment Plant west to Toronto Street would be predominately passive in character and will include: . an 800m long, 3m wide asphalt waterfront trail . connecting trails leading from the various park features to adjacent roads and parking lots . seating areas and lookout platforms located along the top of the bank providing vistas out over Lake Ontario . flexible open lawn areas for events or multi-use activities . a parkette at the south end of Port of Newcastle Drive will be the focal point of phase one and will be the main access point from the neighbourhood to the park. It would include play grounds, seating areas and a gazebo . two public parking lots along the south edge of Lakebreeze Drive . landscaping including seeding, sodding and tree planting The existing bluff is a significant constraint to providing a safe and accessible park. The conceptual waterfront plan proposes to reduce the bluff by re-grading it to a 2:1 slope, and protect the shoreline from further erosion with armour stone. REPORT NO.: EGD-14-05 PAGE 4 The preliminary cost estimate for Phase One of the conceptual waterfront plan, from the Region's Water Treatment Plant to Toronto Street, not including bluff grading or shoreline stabilization, is $1.1 million. 2.2 PHASE TWO PARK DEVELOPMENT (Attachment 3) It has yet to be determined how much public land will exist east of the Regional Water Treatment Plant. This portion of the conceptual waterfront plan is currently in Kaitlin's ownership, with the Municipality having a 15 m easement along the lake edge. The Municipality is currently in discussions with Kaitlin to determine the extent of potential public park space. The conceptual waterfront plan proposes higher order active facilities in this area such as tennis courts, water play, an event area with bandshell/pavilion, formal gardens a washroom building, and community meeting rooms. This portion of the conceptual waterfront plan may require revision or a joint use agreement depending on whether the land is owned, developed, and maintained by the Municipality. The park development at the mouth of the Graham Creek and south of the Brig would be Phase Two of the District Park development. The timing of this phase could be coordinated with Kaitlin's proposed development in that area. The estimated cost to the Municipality for Phase Two will depend on the amount of public land obtained in this portion of the site and proposed uses. 3.0 COASTAL ENGINEERING ASSESSMENT The waterfront lands for the park include approximately 760 meters of existing bluffs. To increase public safety the conceptual waterfront plan proposes to eliminate the bluff by re-grading at a 2:1 slope and installing toe protection at the waters edge to control erosion. At selected locations a terraced access pathway could be incorporated into the slope to provide closer access to the waters edge. REPORT NO.: EGD-14-05 PAGE 5 W.F Baird and Associates - Coastal Engineers were retained to review the conceptual plan specifically as it relates to coastal engineering issues. The objective of the study was to assess and report on the technical and engineering aspects of the proposed stabilization works. The study focused on two primary tasks: 1) Provide a description of the cohesive shoreline and establish shoreline recession rates. 2) Review the proposed stabilization method and provide alternative approaches. 3.1 GENERAL SHORELINE DESCRIPTION Typically the shoreline along the south edge of the parkland is dominated by steep bluffs, which rise 9m to 13m above the lake. The eroding bluff shoreline is classified as a "cohesive shoreline". Approximately 40% of the lower Great Lakes shorelines are cohesive. The bluffs are glacial till with minimal vegetation on the steep bluff face, indicating ongoing erosion. A relatively narrow coarse sand, gravel, and cobble beach is located along the base of the bluff. The beach width varies with fluctuations in water level. Ownership of the lakebed up to the high water mark rests with the Crown under the jurisdiction of the Ontario Ministry of Natural Resources. Using air photos, Baird was able to calculate the amount of erosion since 1955 along the 760m stretch of bluff. In general, the easterly portion of the bluff has retreated a greater distance, typically 9m to 20m since 1955; average annual rate .2m to .45m (8"-18" per year). The westerly portion of the bluff has retreated 3m to 9m since 1955; average annual rate less than .2m (8" per year). Without some means of protection the erosion of the cohesive shoreline material is irreversible and ongoing. REPORT NO.: EGD-14-05 PAGE 6 3.2 SHORELINE PROTECTION ALTERNATIVES At existing rates the bluff would retreat 20m to 40m over a period of 100 years. If remedial action is not taken the waterfront access and parkland will eventually be lost. The existing high steep bluff also poses a risk to those using the parkland. Armour Stone Revetment The conceptual waterfront plan recommends a basic armour stone revetment at the waters edge. This can provide some shore protection for a period of time, but is not a long term solution. The controlling process for erosion of the bluff is the downcutting or downward erosion of the lakebed by wave induced forces. For effective long term shore protection the design must not simply armour the waters edge but must extend to the lake bottom to eliminate the downcutting that causes the erosion. A typical revetment structure must be of sufficient size and height to resist wave attack and ice forces. It would crest above lake level and extend directly into the water (Attachment 4). The slope of the structure face would not allow access by people to the waters edge and the existing cobble beach would be eliminated. This type of revetment has been used effectively along the Scarborough Bluffs. In Scarborough the revetment structure was built, but the bluffs have not been re-graded. Instead they have been allowed to self stabilize. Both re- grading and self stabilization result in the loss of tableland at the top of the bluff. The cost of a full revetment structure would be in the order of $2,000 per linear meter of shoreline protected. Maintaining the existing width of tableland at the top of bluff would require massive quantities of fill extending approximately 20m into the lake to achieve a 2:1 slope. This is not considered a feasible approach for this project because of the high cost and impacts on fish habitat. The main elements of the conceptual waterfront plan could still be constructed despite the loss of tableland. REPORT NO.: EGD-14-05 PAGE 7 Detached Breakwaters and Artificial Headlands Detached breakwaters are island structures made of stone that are located 100m to 150m offshore parallel to the shoreline (Attachment 5). They are intended to reduce wave energy before reaching the shoreline. They can be constructed as a continuous structure or a series of structures separated by gaps and they can extend above the water level or be submerged just below the water level. Artificial headlands are similar to detached breakwaters except that they typically have some form of perpendicular connection to the shore to contain alongshore transport of sediment (Attachment 6). They are generally located closer to the shoreline. Artificial headlands are often used to protect and retain placed beach material. The two primary advantages to detached breakwaters and artificial headlands are: 1) The erosion protection is located offshore which permits the preservation or enhancement of the existing shoreline. 2) The beach area created behind the breakwaters or headlands provides a valuable waterfront resource for public use. The disadvantages of detached breakwaters and artificial headlands are: 1) The extent of lake bed occupied by the structures and the beach fill are significant and would be subject to extensive review under the federal Fisheries Act. 2) There could be potential impacts on downdrift shorelines that would have to be assessed. 3) High cost, typically $4000 per meter of protected shoreline. 4.0 CONCLUSION The Municipality will own or have access easements over most of the land along the Lake Ontario shoreline between Toronto Street and the mouth of the Graham Creek. The land will be a valuable resource for public use and enjoyment. The conceptual waterfront plan prepared for the land is appropriate as a guide for the future development of the parkland. The parkland will most likely develop in phases and detailed design for REPORT NO.: EGD-14-05 PAGE 8 each phase will carefully examine proposed uses in context with the recreational needs of the area and site conditions. With the ownership of the land comes the responsibility for controlling the erosion of the bluff. Without some means of protection the erosion of the Port of Newcastle shoreline is irreversible and ongoing. If the Municipality intends to construct a linear waterfront park adjacent to the eroding shoreline a long term solution must be implemented. Based on the effectiveness and cost of the various shoreline protection alternatives, it is recommended that armour stone revetment be installed along the 760m of existing bluff at an estimated cost of $1.5 - $2 million. The bluff should also be re-graded to a 2:1 slope for the protection of the public using the park. Kaitlin, the subdivision developer, has confirmed that they could accommodate the fill material removed from the re-graded bluff within their next phase of development. They have also agreed to perform the grading at their cost starting in the spring of 2005. This initiative will enable the Municipality to avoid this cost in the future, a potential savings of $400,000-$500,000. The re-graded slope will eventually need some means of erosion protection; however, the work could be deferred until funding is approved. Once the bluff grading is completed, the Municipality could consider establishing a section of waterfront trail from Toronto Street to the Region's Plant. Further components of the plan could be added subject to Council's direction. Funds for the installation of erosion protection and for the development of the waterfront park should be included in a future Capital Budget and Forecast. Attachments: Attachment 1 - Land Ownership Attachment 2 - Conceptual Waterfront Plan Phase I Attachment 3 - Conceptual Waterfront Plan Phase II Attachment 4 - Armour Stone Revetment Attachment 5 - Detached Breakwaters Attachment 6 - Artificial Headlands .. Ul o - l: o ~ o ~ <Ii .. Ul i 11{ W~~ s DRAWN BY: E.L. DATE: April 18, 2005 REPORT EGD-14-05 ATTACHMENT NO.1 ~ ,. " '" 0 >: '" m .... m "tl Z ,. " i j~ 0 Gl " 5~~?i:E' 0 :;; ';':!ieJ~~ '" J ;0 Z 0 .... ~(') --i 2~~",~ m m G) " "tImo, 0 m B~~~~ I' r j;;oz " ;0 i5<.il5~N . , cn"T1(') Z Z ~~~~ B I m~~ -H",?OlZ 6 m Gl ~ .iiiE '" . OZ'" :E ~ ,~ > (fl ~ Z"'C: ~ ~o m.,,> (") m > )> ~ 0':' ~i ~ s;:r- (fl ~ ~ <.il ..,,- 6 ~" Z --i ('i -" ~5 ilfl" r- en ~~ ~ ~ m m -< J (fl ~~ c ~ i ~ c -.----~I ( , , , ~ ~ , o . '. ~ , Ii ~J -------------- ~ /~ -----u ': 1="-1: Iii 1 11\ \\L~ II \\U.l= I ! 11( if~::= -t-- i~ ~ r- n o Z Z fl1 n -1 6 Z lD ;;: > ~ Z > n r- C OJ :I 0 c lD fl1 >-0 Z:I 0> ",lD r- fl1fl1 :>0- nN '" " fl1 rT1 ~ 6 0 Z <: > .... r- :>0- -n > :u n - r= 0 =i ni lD ~ ;0 m m ." " "U Z 0 i ~C ;0 ~ 0 G) ... ;;0 m I!~ "'0--10 -l Z Gl ,~ m '? ,. :rmo 0 m ,r ~ )>;:02 'TI ;;0 1" cn'"T10 Z 0 m;:Om Z '" " ~o"'O m G) > 2--1 :E r.I --1C (J) ,. () ::I > 0"'0 )>, m 'D ~ > '" S;:' ;;0 (.0.)'2' r (J) < '" ,. 2 -l ~ () z r .... ~ z " m m " . ~ (J) c , ~ z " o 1" (J--- ) 1 '1_-----' , / ,- L,--- I '" ,--....., \ \ \ I \ / , l;~ 5 ~ n ;flJl - ~ ~ :}: ~ ~ , o z v "'~;,yt;;-- >~ !i ~;'" :1 "~(" -',' " l' , ), 1, ':' I' " I' " ~c >c ,~ "" ~, c~ ~~ ,0 , 0 \.... '\ Z; ...., -, [:=J\" ''---,'' -----,:;- .- , ~ ' " )>: " "t: v~_:~~ j~."f' ,/-\'{/ .?\V' ~J>':~,J S,V;~- <""':of" z ".}(/ v~-? (;) /~,y ,4V < .?'V ?::.?,,)> ",.Y,\:..;? r,<<~ .y />t, - v~~~:/ -J' > ~ I ~ ",cn ,< , ,~ Q cZ z' < 0," p )>~ ~ i'ir ~ ,ri >, " A 9~ " ,. Z ~z " _C'l I \""", AV A,."y A\1f' ~V """ ""'V ?-,:V ~'If' A"" "P"1t"" ?f 'v A"""", v"\',v" ~ ;;\f\~ ~ - I ~ ~\ ~, ~ ~.I;:. ~ ~ ~ ~ ~ ~ ~ ~ > ~ , ~ ~ 8 c z o r' / II II -J )>z::E ~n,. ,.rr ~~~ ~~~ ~CII)> ....'z C~'=J ~::I(;) }l~ ,C z" orr. ri z z ~ c Q ~ ,,-, I ~g~~ c:j)>G;o s::~Z;::I""1J lJ12~8@ CIllUcrn R8s::~ S::"-=)>O rn-"ZO ",)>00 :::In :J\ 3~ D , $>=- Armour Stone Revetment at Fishleigh Drive, Scarborough Bluffs " ~""""",-, Natural recession ....... of profile If unprotected "Protected" shoreline "--- -..._- ----- p~e?el"~.tor: F'~J"mlt5 '..roger w.v~~tpf'lt;t:.ack $h9t"eht't46tt"u~t:ur"e ...~~ " ',,' ,',,' '-.- - ~OI"r'i!Jmatnellr$hOr~ -~-~~::,~::~:-::~::::~n~--- of nearshore profile: ------------ Eventual undermining Future Undermining of Structure Due to Downcutting REPORT No. EGD-14-05 ATTACHMENT No.4 Plan View Existing Profile Bf~<1ch Fill Detached Breitkwater 1 Cross-Section A-A Alternative Detached Breakwaters Detached Breakwaters REPORT No. EGD-14-05 ATTACHMENT No.5 Artificial Headlands bl~in8Shufdjnp Artificial Headlands Lake Forest, Illinois Eastern Beaches, Toronto REPORT No. EGD-14-05 ATTACHMENT No.6