REPORT
Meeting:
Date:
CORPORATE SERVICES DEPARTMENT
General Purpose and Administration Committee
February 23, 2009 Resolution #: (7T ~J ~'
Report #: COD-015-09, File #: By-law #:
SUBJECT: GARNET B. RICKARD RECREATION COMPLEX LEASE SPACE -
COMMUNITY CARE DURHAM
Recommendations:
It is respectfully recommernded that the General Purpose and Administration Committee
recommend to Council the following:
1. THAT Report COD-015-09 be received;
2. THAT Council provide staff direction with respect to the proposal from Community
Care Durham to lease the vacant space at the Garnet B. Rickard Recreation
Complex; and
3. THAT Community Care Durham and the Clarington Older Adults Board be
advised of Council's decision.
Submitted by: Reviewed by: _ -wl
Marie Marano, H.B.Sc., C.M.O., Franklin Wu,
Director of Corporate Services Chief Administrative Officer
tn~
Nancy Taylpr, B.B.A., C.A.
Director of FinancelTreasurer
MMlJBMm
CORRPORATION OF THE MUNICIPALITY OF CLARINGTON
40 TEMPERANCE STREET, BOWMANVILLE, ONTARIO L1C 3A6 T(905)623-3379 F (905)623-4169
REPORT NO.: COD-015-09
PAGE2
1. BACKGROUND
1.1 At their meeting of November 10, 2009, Council provided staff with direction to proceed to
negotiations with Community Care Durham (CCD) for lease of space required to house
Community Care staff and operations currently located at the Clarington Beech Centre. This
was in response to a letter from Community Care Durham, dated October 14, 2008, indicating
that they were interested in pursuing this approach after determining that the cost to convert
the site at GBRRC to house both the Bowmanville office and the Newcastle Adult Day
Program in a single facility was cost prohibitive. A copy of the letter is attached as Schedule
,.A„
1.2 .Discussions began with Community Care Durham in November 2008 and space requirements
were determined to be in the area of 2,000 square feet. Once the space requirements were
determined Durham Community Care staff went back to their space consultant to determine
office layout then to their contractor to establish an estimated to construct the office space
required to house staff from their Beech Street Offices.
1.3 By email dated February 4, 2009 Durham Community Care, (Schedule "B° attached) provided
notice that they had found the cost to construct the required offices to be prohibitive. They
also reiterated that their preference was to relocate both the Bowmanville office and the
Newcastle Adult Day Program to the same facility. With this in mind, CCD proposed that they
were interested in acquiring the complete GBRRC space of 5,005 square feet at a gross lease
of $13.00 per square foot. A gross lease includes all utilities, snow clearing and waste
removal. This proposal is contingent on the Municipality constructing the required space,
including offices, washrooms, kitchen facility, improved access, additional windows and use of
the patio.
1.4 The lease rate did. not speak to the issue of G.S.T. (5%) which is normally extra to the lease
rate. In this case with the G.S.T extra it would amount to $0.65 per square foot. If CCD is
working on the assumption that the $13.00 rate includes G.S.T. the actual lease rate per
square foot would be $12.38 per square foot.
1.5 CCD and the Older Adult Board have been provided a copy of this report at the time of
signature to allow representatives to speak to the proposals at GP&A.
2.
2.1 For comparison purposes the following schedule provides a comparison of the proposed
lease submitted by Community Care Durham against alternate options together with a
breakdown of the original proposal received in response to the RFP issued in 2008.
REPORT NO.: COD-015-09
LEASE OPTIONS
Direction Re nested: O lion A O lion B
Garnet B. Rickard Recreation Complex CCD Staff Proposal
Total Space Available - 5005 sq. ft. 2009
Pro osal
Lease hold Improvement Costs
Municipality Cost -Maximum Approval $600,000.00 $600,000.00
Community Care Durham Cost NIL NIL
Utilities Included Extra
GST Not specified Extra
Annual Revenue
Assuming GST Extra or $65,065.00 $100,100.00
Assumin GST Included $61,961.90
Time required too recover municipal
investment.
Assuming GST Extra or 9.22 yearsl'~ 5.99 years
Assumin GST Included 9.68 earsl'~
Actual revenue eamed in
5 years NIL NIL
10 years GST Extra or $50,750.70iZ~ $401,401.00
10 ears GST Included $19,827.81 cz>
Escalation Clause Not included ~ CPI or
reasonable
inflation rate
UTILITY OPTIONS
PAGE3
Option 1 Option 2
Staff Pro osal
Lease format for the selected Gross Lease including utilities, Net Lease, excluding utilities,
lease rate in Option A or B heat/AC, snow clearing, waste heat/AC, excluding GST
removal, excludin GST
Term -Recommended 10 year, with 10 year option to renew if conditions remain acceptable to
the Municipality.
Notes
(1) This does not consider the cost of utilities or the lost interest on funds used for lease hold
improvements
(2) Utility casts are not factored into this calculation.. Estimated utility cost per year for the leased area
- $16,500.00, based on 2007 calendar year.
(3) FOR COMPARISON
$15.00 =Annual Revenue $75,075.00, Payback 8 year, GST and Utilities paid by CCD
$17.00 =Annual Revenue $85,085.00, Payback 7 years, GST paid by CCD; Net Lease
REPORT NO.: COD-015-09 PAGE 4
2.2 Lease Hold Cost /Recovery Now Proposed by CCD at $13.00/sp. ft. Lease Rate:
Based on a square footage of 5,005 square feet and the lease rate offered by CCD the annual
lease revenue would total $65,065.00 exclusive of 5% G.S.T. paid by CCD. It is estimated
that the construction and completion costs per CCD's proposal would be approximately
$600,000.00 estimated on Schedule "C"; therefore it would take approximately 9.22 years to
recover the casts with no revenue realized until after that time. CCD has also offered a 10
year extension which will provide total revenue of $701,300.00 total revenue over the 20 year
proposed life of the lease. These figures are based on the lease rate remaining constant
throughout the lease period. If the lease rate proposed is meant to include GST the payback
period increases slightly to 9.68 years. If an inflation factor is build into the arrangement, the
payback would improve as would the revenue over the lease period.
2.3 The 10 year recovery does not take into account the cost to heat, air condition and light the
facility. The estimated annual utilities cost would be $16,500.00, based on average 2007
Rickard Arena costs. When these elements are taken into consideration the payback period of
the construction cost increases.
2.4 Please note that this is a very rough estimate and would require confirmation of cost estimates
by an architect. This estimate does include architectural services including project
management at approximately $85,000.00.
2.5 Initial 2008 Proposal by CCD:
In the initial discussions with CCD in 2008 when the Municipality was providing approximately
$205,000.00 in leasehold improvements and CCD was covering the office construction
estimated at approximately $250,000.00, the pay-back period for municipal investment was
estimated to be approximately 3.41 years.
2.6 Given that the current proposal will require the municipality to invest $600,000.00 not
contemplated in the budget, the funds will have to be provided from reserve funds. The
proposals do not assess the lost opportunity cost (foregone interest) in the amount of
approximately $119,400.00 for 5 years (interest rate estimated at 3.98%) or approximately
$273,600.00 over 10 years (interest rate estimate - 4.56%), in determining payback and the
viability of this proposal. Also, this report does not speak to the matter of potential revenue
from tenants who may not require significant leasehold improvements.
REPORT NO.: COD-075-09
PAGE 5
2.7 Working on the assumption that a 5 year pay-back which was reasonably close to the
municipality's investment contemplated in the 2008 discussions was an acceptable
arrangement, the lease rate on the proposed arrangement put forward by CCD would require
a lease rate of approximately $20.00 per square foot.
2.8 One of the areas noted in the CCD a-mail of February 4th, Schedule B, is the requirement of
the patio with fencing. This requirement has been reviewed with Community Services and this
area has been traditionally used by Community Services programming staff and in
addition, various groups renting our Multi Purpose area of the facility, especially the many
weddings and banquets, where the adjoining patio has served quite useful. Under the
circumstances, unless a sharing arrangement could be made, this requirement could not be
met. Please note that the total construction cost estimate retains the value of the patio in the
event a sharing arrangement can be made otherwise it will be deleted from the construction
estimate.
3. FINANCIAL IMPLICATIONS
3.1 It is recommended that should Council approve moving ahead with construction, an upset limit
be established at $600,000.00. The funds are recommended to be funded from the General
Municipal Purpose Reserve Fund.
3.2 Council is facing a complex issue of accommodating the spatial requirements of the Older
Adults Association which is a municipal mandate. At the same time it may be advisable to
consider the potential ramifications for the request from CCD to set a precedent for other non-
municipal agencies who may wish to seek accommodations at a reasonable rate with no
investment from the requesting agency.
4. CONCLUSON
4.1 After reviewing the proposal from CCD it is expected that costs to complete the renovations
will be high and the requirement to provide a reasonable payback would make the lease rate
at $20.00 unmanageable for CCD.
4.2 Under the circumstances staff request direction. Alternatively, Council may wish to provide
staff with direction to cease discussions with CCD and issue a new RFP for the lease of the
space to one or more proponents (The municipality has been approached by at least three
firms/individuals interested in leasing space at the GBRRC since the original RFP).
REPORT NO.: COD-075-09
PAGE 6
4.3 In either option staff would provide a report and recommendation on the results of the
construction tender options and a final lease for the GBRRC space, or the RFP process..
4.4 Community Care Dufiam is currently an over-holding tenant at the Beech Street location as
their lease expired October 31, 2008. Staff will be providing a subsequent report on this
matter once this report is dealt with and staff has direction.
4.5 This report has been reviewed for recommendation by the Purchasing Manager and the
appropriate department and circulated as follows:
Concurrence: Director of Community Services
®Community Care Durham
Clarington
COPE Mental Health
Program
Indivklual Suppod
Group Suppod
Education
Home Support
Program
Meals on Wheels
Transportation
Accessible Van
Friendly Visiting
Fool Care Clinics
Luncheon Out
Telephone Reassurance
Home Maintenance
Home Help
Respite Program
Adult Day Programs
In-Home Respite
Offices Serving
Ajax-Pickering
Brock
Clarington
Oshawa
Scugog
Uxbridge
wnimy
Charitable Reg.#
1 L888 9955 RROOOL
Volunteer and
become an
everyday hero
A United Way
Member Agency
October 14, 2008
Mr. Jerry Barber
The Corporation of the Municipality
of Clarington
Manager Purchasing Office
40 Temperance Street
Bowmanville, ON L1C 3A6
Deaz Jerry:
SCHEDULE "A"
26 Beech Avenue
Bowmanville, ON LiC 3A2
COPE Mental Health Program
Te1:905-623-4123 • Fax:905-623-2604
Home Support Program
Te1:905-623-2261 . Fax:905-623-2604
Respite Program
Adult Day Program
Tel:1-888-255-6680. Fax:905-837-6768
www. communitycaredurham.on.ca
Re: Lease Agreement between Community Care Durham and the
Municipality of Clarington for office space at 26 Beech Avenue
Further to recent correspondence with the Municipality of Clarington and the
determination that there are currently no suitable locations in the Clarington azea in
which to expand our programs, Community Care Durham (CCD) is requesting a lease
renewal for office space at 26 Beech Avenue. As you are aware we aze also seeking
additional space at the Beech Centre.
On June 5, 2008, Community Care Durham submitted a proposal to the Municipality
of Clarington to lease 5005 squaze feet of space at the Garnet B. Rickard Recreation
Complex. This new space would have allowed Community Care Durham to operate
all of their Clarington community support services from the one location, including the
Adult Day Program.
Due to the present dysfunctional layout for office space at the Rickard Centre, and
based on feasibility drawings and an estimate from a contractor, it was deemed that the
cost to improve this space would be far too substantial for Community Dare Durham
to absorb.
However, should the Municipality undertake to renovate this space for office use
(including windows) CCD would be agreeable to relocate their Home Support and
COPE programs presently serviced from the Beech Avenue location. Converting this
space to office use would also allow for a variety of other office tenants to share in this
space, including perhaps a meeting room that could be rented.
Helping people Live at home
SCHEDULE "A"
Mr. Jeny Barber
Municipality of Clarington
October 14, 2008 Page 2
Community Care Durham's references will attest to our stability, long term tenancy and timely
monthly payments.
Thank you for your assistance in this matter.
Sincerely,
~~ .~
~~
Barbara Morcott
Director, Administration & Finance
cc: Mayor Jim Abernethy, Municipality of Clarington
Frank Wu, Municipality of Clarington
Brent Farr, Community Care Durham
Sally Barrie, Community Care Durham
Page 1 of 2
SCHEDULE "B"
Barber, Jerry
From: Brent Farr [bfarr@communitycaredurham.on.caj
Sent: Wednesday, February 04, 2009 10:35 AM
To: Barber, Jerry
Cc: MayorsExternalMailGroup
Subject: Garnet B. Rickard Recreation Complex
Hi Jerry,
In follow up to your email and telephone call to Barb Morcott last week, this will set out Community
Care Durham's position regarding our potential move to the Garnet B. Rickard Recreation Complex.
Subject to the satisfaction of the challenges presented in this correspondence, Community Care Durham
would be prepared to offer the Municipality of Clazington a ten year lease, with a ten year option to
renew, on the 5,100 square feet of space in the Rickard Complex to move both our Home Support and
COPE office (currently located in the Beech Centre) and ow Adult Day Program (currently located in
Newcastle).
Rye would be prepared to offer $13.00 per square foot on a gross lease basis. As a result of an expansion
of the existing space for these programs and an increase in lease rate compazed to the Beech Centre,
Community Care Durham would incur an additional $22,000 per yeaz in rent costs based on this $13.00
per square foot.
Due to our organizational needs and new integration initiatives by the Central East Local Health
Integration Network (our primary fonder), it is considered prudent that we collocate the Home Support,
COPE, and Adult Day Program together.
In order for this move to be viable for Community Care Durham, we aze in a financial position to only
invest funds in our own interior furnishings and equipment. Therefore, the challenges we face in order
to make this new space in the Rickard Complex "office appropriate" are:
. Ample exterior windows (as feasible)
. Two private accessible washrooms in designated Adult Day Program
. Kitchenette with sink in designated Home Support /COPE area
. Roughed-in plumbing for a full kitchen in the Adult Day Program
• Approximately six completed offices in designated azeas
. Tile or carpet floor coverings in designated areas
• Drop T-bar ceiling
. Patio with fencing
. Sprinkler system as required by code on finished space
. Soundproofing in areas where required (e.g. between gym and Community Care)
I recommend that we attend a meeting with the Mayor and the appropriate Municipal department heads
as soon as possible to move this opportunity forward as it has been some time since we commenced
negotiations.
Thank you,
Brent Farr
2/13/2009
Page 2 of 2
SCHEDULE "B"
Brent Farr
Executive Director
Community Care Durham
419 King Street West, Unit 605
Oshawa, Ontario L1J 2K5
Email: bfarro~communitycaredurham.on.ca
Tel: 905-404-2224 ext. 25
Web Site: www.communitycared.u..rham.on.ca
Supporting Peop/e, Strengthening Community
Confidential: This email and any attachments transmitted with it are confidential and intended
solely for the use of the individual or entity to which they are addressed. If you have received this
email in error please notify the sender and delete the a-mail immediately. If you are not the
intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.
Le present courriel (email) et les documents qui y sont attaches sont confidentiels et proteges et
s'adressent exclusivement au destinataire mentionne ci-dessus. L'expediteur ne renonce pas aux
droits et obligations qui s'y rapportent. Toute prise de connaissance, diffusion, utilisation ou
reproduction de ce message ou des documents qui y sont attaches, ainsi que des renseignements
que chacun contient, par une personne autre que le destinataire designe est interdite. Si vous
recevez ce courriel par erreur, veuillez m'en aviser immediatement et veuillez le detruire avec les
documents qui y sont attaches.
No virus found in this outgoing message.
Checked by AVG.
Version: 7.5.552 /Virus Database: 270.10.17/1934 -Release Date: 2/4/2009 8:24 AM
2/13/2009
SCHEDULE"C"
ESTIMATED CONSTRUCTION ELEMENTS AND COST
Estimated Cost of
Construction elements
Fire Rating $30,000.00
Addition of windows on south facing wall and east facing wall $35,000.00
Plumbing for Washrooms & Kitchen $40,000.00
Flooring $25,000.00
Ceiling $60,000.00
Offices, kitchenette and washrooms $250,000.00
Patio $25,000.00
New entrance from exterior of Building $25,000.00
Contingency $25,000.00
Design and inspection $85,000.00
Total Capital Cost (maximum limit of approval for project) $600,000.00"
" Estimates have been confirmed with an architect as being reasonable.